Cross Island Line Construction
Pages
(Move to ...)
Home
Contact Us
About Cross Island Line (CRL)
List of Cross Island Line (CRL) Contracts
CRL1 Project Information Centre - Hougang
CPE Project Information Centre - Punggol
CRL2 Project Information Centre - Clementi
CR02 - Aviation Park [CR103]
CR03 - Loyang [CR106]
CR04 - Pasir Ris East [CR107]
CR05 | CP01 - Pasir Ris [CR108]
CR06 - Tampines North [CR109]
CR14 - Turf City [CR203]
CR15 - King Albert Park [CR205]
CR16 - Maju [CR206]
CR17 - Clementi [CR208]
CR18 - West Coast [CR209]
CR19 - Jurong Lake District [CR211]
Tunneling contracts [CR102, CR105, CR110, CR202, CR207, CR210]
▼
Monday, July 7, 2025
CRL2 Groundbreaking ceremony
›
7 July 2025 - A group photo with contractors of CRL2. Today, the Land Transport Authority (LTA) held a groundbreaking ceremony to mark the o...
Saturday, July 5, 2025
CPE - A snapshot in June 2025
›
An overview of Riviera & Punggol stations along the CPE in June 2025. Having missed out covering the remaining 2 stations along the Cros...
Thursday, June 26, 2025
N109A - Completion of Exit 2 subway
›
June 2025 - Completed Rectangular Tunnel Boring Machine drive for Exit 2 subway. Image from LinkedIn This month, a milestone has been achi...
Sunday, June 8, 2025
CRL - A snapshot in May 2025
›
An overview of CRL1 contracts CR101 - CR111 as of May 2025. Top (L - R) : CR101 - Changi East Depot, CR102 - Tunnels, CR103 - Aviation Park ...
Tuesday, April 15, 2025
CR116 - TBM assembly begins
›
March 2025 - Assembly of the slurry TBM that will bore tunnels for the contract has commenced within the launch shaft. Source: LinkedIn Re...
Sunday, April 6, 2025
CR208 - Clementi EWL A&A works for paid transfers
›
Brochure for contract CR208's Clementi station. A common hot topic question that has been asked many times has been - will Clementi stat...
Thursday, April 3, 2025
CR111 - TBM Daphne
›
14 February 2025 - Group photo during the Geotechnical Society of Singapore's visit to contract CR111's launch shaft with TBM Daph...
›