Saturday, December 14, 2024

CR112 - TBM assemble!

 

13 December 2024 - The TBM tail shield during lifting operations.

Contract CR112 has made some headway since the arrival of the Tunnel Boring Machines (TBMs) at the site. Two TBMs will be used to bore the twin tube tunnels towards Serangoon North station. After a public name voting process, the TBMs are to be named Artemis & Valkyrie. Parts of the first TBM were lowered into the launch shaft on 7 December 2024 and the tail shield was lifted in on 13 December 2024.

Monday, December 2, 2024

CR202 - A large TBM for a large tunnel

 

A view of the front of the TBM.
Source: Herrenknecht

Recently, German tunnel boring machine (TBM) manufacturer - Herrenknecht - uploaded several images of the machine numbered S-1365 onto its website. The TBM will be used for contract CR202 to construct the large diameter single bore tunnel through the Central Catchment Nature Reserve, connecting Cross Island Line (CRL)'s phases 1 and 2. The contract, won by a joint venture between Obayashi & Shanghai Tunnel Engineering Co, was the first of several CRL2 contracts to be awarded.

Friday, November 15, 2024

CR108, CR115 & CR205 - Traffic diversions & temporary road closures

A compilation of diagrams detailing upcoming road diversions, temporary road closures &
changes to the road networks over the weekend of 16 & 17 November near 3 CRL work sites.

The weekend of 16 & 17 November will be a busy one for the Cross Island Line (CRL) with various traffic diversions, temporary road closures & changes to road schemes taking place across three different projects over 2 phases of the line. The works in particular will affect residents in Pasir Ris at the site of contract CR108, in Ang Mo Kio near site CR115 at Tavistock station and at King Albert Park at the site of CR205.

Monday, November 11, 2024

CR211 - Further information

A screenshot from the webinar, showing Jurong Lake District station's Exit 3 design.

A recent webinar held online by the Bentley to market building information modeling software Synchro allowed viewers to obtain some additional information on Jurong Lake District station under contract CR211. The Cross Island Line (CRL) phase 2 station will be built with an initial 3 exits and two cut & cover tunnel sections on either side of the station. These are known as the Western Cut & Cover Tunnel (WCCT) and Eastern Cut & Cover Tunnel (ECCT).

Tuesday, November 5, 2024

P103 - Another milestone with TBM cutterhead assembly

 

4 November 2024 - A photo of the visiting delegation in front of the TBM's cutterhead.
Source: Facebook

Contract P103 has reached another milestone with the assembly of tunnel boring machine (TBM)'s cutterhead. Various parts of the machine's shield have already been lowered into the launch shaft which is located outside Pasir Ris camp. Some further assembly is still required before the machine will be launched for its first 3.4km drive towards Punggol station, where it is expected to arrive in mid-2026.

Thursday, September 26, 2024

CR211 - Telegram channel launch, CR115 - TBM launch & CR112 - TBMs named

 

A render of the Jurong Lake District station being built under contract CR211.
Source: LTA

20 September 2024 - The launching ceremony for tunneling under contract CR115.
Source: LinkedIn

Tunnel boring machines for contract CR112.
Source: Forms.sg

We have a quick update on some developments along the Cross Island Line (CRL) to share: The launch of contract CR211's Telegram channel & TBM #1 for contract CR115 and confirmed names of the tunnel boring machines (TBMs) for contract CR112. More information after the jump.

Friday, September 6, 2024

CRL - A snapshot in August 2024

 

An overview of 2 CRL1 contracts as of August 2024.
Top: Changi East depot
Bottom: Contract CR110 launch shaft at Paya Lebar Air Base

Overview of CRL1 stations CR3 - CR11 as of August 2024.
Top (L - R): CR3 - Loygang, CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris
Middle (L - R): CR6 - Tampines North, CR7 - Defu, CR8 - Hougang
Bottom (L - R): CR9 - Serangoon North, CR10 – Tavistock, CR11 – Ang Mo Kio


Overview of CRL1 stations CR12 – CR13, CPE stations CP2 – CP4 & CRL2 stations CR15 –
CR18 as of August 2024.
Top (L - R): CR12 – Teck Ghee, CR13 – Bright Hill, CP2 – Elias
Middle (L - R): CP3 – Riviera, CP4 – Punggol, CR15 – King Albert Park
Bottom (L - R): CR16 – Maju, CR17 – Clementi, CR18 – West Coast


With the award of contract CR207 for tunnels between Maju and Clementi stations in August, all civil contracts across the Cross Island Line (CRL)'s phases 1, 2 and Punggol extension have been awarded. Work on phase 1 and the Punggol extension were well underway while works along phase 2 were at different stages owing to the contract award progress.