Saturday, August 8, 2026

CRL - A snapshot in July 2026

A compilation of the various sites across Phases 1 and 2 in July 2026.

With the announcement of the Cross Island Line (CRL)'s final phase on 31 July 2026, we now know that the line will stretch for 67km, making this line the longest in the country - beating out the East-West Line (EWL)'s record of 54km by a fair bit. This means that the CRL is a really big project, spanning end-to-end across the entire country. While the EWL also crosses the island from east to west, it mostly sticks to the southern section of the island. In comparison, the CRL swings further north and south than the EWL, making its route much more varied and spread out. This translates into it being much more difficult to easily visit and keep track of all contract sites.

For this update, we tried to cover as much ground as we could to give you an idea of where the line stands in progress. As phase 3 was only announced right at the end of the month, we won't be yet including that section in this update. Nonetheless, all the previous phases of the line that were officially announced are covered in this update in some way, form or manner. There's a lot to unpack, so jump right on in after the jump.

Thursday, April 30, 2026

CPE - A snapshot in April 2026

Overview of CPE stations as at April 2026.
Top: CP2 - Elias
Middle: CP3 - Riviera
Bottom: CP4 - Punggol

We're beginning the April snapshots with a recap of the Cross Island Line's Punggol Extension (CPE) where things are beginning to ramp up as tunneling works for the entire length of the phase commence. Station works have also progressed at the three station sites under this phase of the line. Find out more as we cover the brief summary of progress made at each station site.

Sunday, March 8, 2026

CRL - A snapshot in February 2026

Overview of CRL1 stations CR2 - CR5, CR8 - CR10 & CPE station CP4 as at February 2026.
Top (L - R): Changi East Depot, CR2 - Aviation Park, CR3 - Loyang
Middle (L - R): CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris, CR8 - Hougang
Bottom (L - R): CR9 - Serangoon North, CR10 - Tavistock, CP4 - Punggol

It's been a while since we've had a Snapshot update for the Cross Island Line (CRL). Here's one from February 2026, covering several of the sites across Phase 1 and Punggol station along the Punggol Extension. How have works progressed, especially at the line's eastern end? We find out all that and more in this update after the jump.

Saturday, July 5, 2025

CPE - A snapshot in June 2025

An overview of Riviera & Punggol stations along the CPE in June 2025.

Having missed out covering the remaining 2 stations along the Cross Island Line (CRL)'s Punggol Extension (CPE) in the CRL May 2025 snapshot, we visited these station sites in June to catch up. The sites were hives of activities, especially with a major road diversion at the junction of Punggol Central & Punggol Place being implemented this past month. More details after the jump.

Tuesday, March 25, 2025

P105 - Roadshow exhibition for upcoming footpath closures

 

13 March 2025 - A view of the exhibition boards at the roadshow to update commuters on the
upcoming footpath closures in the vicinity.

The contractor for contract P105 - Woh Hup Pte Ltd - recently held a roadshow over two days at the Punggol station to inform commuters of the upcoming footpath closures. Some of these footpath closures will come in tandem with road diversions to be implemented while others will be implemented in line with phased works for the new underground station.

Friday, September 6, 2024

CRL - A snapshot in August 2024

 

An overview of 2 CRL1 contracts as of August 2024.
Top: Changi East depot
Bottom: Contract CR110 launch shaft at Paya Lebar Air Base

Overview of CRL1 stations CR3 - CR11 as of August 2024.
Top (L - R): CR3 - Loygang, CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris
Middle (L - R): CR6 - Tampines North, CR7 - Defu, CR8 - Hougang
Bottom (L - R): CR9 - Serangoon North, CR10 – Tavistock, CR11 – Ang Mo Kio


Overview of CRL1 stations CR12 – CR13, CPE stations CP2 – CP4 & CRL2 stations CR15 –
CR18 as of August 2024.
Top (L - R): CR12 – Teck Ghee, CR13 – Bright Hill, CP2 – Elias
Middle (L - R): CP3 – Riviera, CP4 – Punggol, CR15 – King Albert Park
Bottom (L - R): CR16 – Maju, CR17 – Clementi, CR18 – West Coast


With the award of contract CR207 for tunnels between Maju and Clementi stations in August, all civil contracts across the Cross Island Line (CRL)'s phases 1, 2 and Punggol extension have been awarded. Work on phase 1 and the Punggol extension were well underway while works along phase 2 were at different stages owing to the contract award progress.

Sunday, April 21, 2024

CPE Project Information Centre - now open!

 

15 February 2024 - A view of the entrance to the CPE PIC prior to the centre's opening.

Earlier this month, the Cross Island Line (CRL) Punggol Extension's (CPE) Project Information Centre (PIC) was officially opened to the public. The PIC is open to the public during weekdays during office hours and is closed on weekends and public holidays. Walk-ins are permitted and no appointment is needed to visit the centre.

Tuesday, February 13, 2024

P105 - One last look at the Punggol station underpass

 

A map of the Punggol North East Line station. The underpass
runs parallel to the station, below Punggol Central and is located
between exits A & D.
Source: SBS Transit

6 May 2023 - A view of the entry point to the underpass from Exit D.

Part of the underpass will be converted into a new exit for the station.

With works for the Punggol station on the Cross Island Line (CRL) - Punggol Extension (CPE) now underway, the existing underpass at Punggol's North East Line station will close come 15th February 2024. The northern part of the underpass will be converted into Exit 7 of the new CPE station box while the southern part will be permanently closed. In future, Exit 5 will connect to the CPE station's concourse level, providing an alternative to the existing underpass. Currently, a street level pedestrian crossing is available for commuters to cross Punggol Central without going through the paid areas of the station. As the crossing is located underneath the LRT platforms, it is also weather-protected. We take one last look at the underpass before its closure on 15th February 2024.

Saturday, December 30, 2023

CPE & CRL2 - year-end update 2023

 

The 9 station sites of CPE & CRL2 as of end-2023.

2023 was an eventful year for both the Cross Island Line (CRL)'s Punggol Extension (CPE) & Phase 2 (CRL2) sections with the ground breaking ceremony and contracts being awarded respectively. With the ground breaking ceremony taking place this year, work has began at all 3 station sites under the offshoot branch which connects the main CRL line at Pasir Ris with Punggol - a precursor to the long spoken about Northshore Line which would have eventually connected Punggol and Woodlands. Over at CRL2, contract awarded began, with 3 of the 9  civil contracts awarded through the year. All in all, 2023 has been exciting for the phase 2 stations.

Tuesday, October 10, 2023

CPE - Groundbreaking ceremony

 

This morning, the Land Transport Authority (LTA) held a groundbreaking ceremony for the Cross Island Line (CRL) - Punggol Extension (CPE) section. Spanning 7.3km and adding 3 additional stations to the line, the ceremony was officiated by Acting Minister for Transport, Mr. Chee Hong Tat. Also in attendance were grassroots leaders for the various districts in which works will take place - Mr. Teo Chee Hean (Pasir Ris Elias), Ms. Yeo Wan Ling (Punggol East) & Mr. Janil Puthucheary (Punggol Central).

Thursday, October 5, 2023

P105 - New video by LTA

 

Source: YouTube

Yesterday the Land Transport Authority (LTA) released a new video flythrough of the Punggol Cross Island Line - Punggol Extension (CPE) station. The video shows the station's four entrances, the eastern concourse area and eastbound platform. The transfer connection to the North East Line (NEL), however, is not shown. This video differs from another one shown by contract P105's contractor Woh Hup at their roadshow.

Source: SGMC YouTube

With the new video released on LTA's YouTube page, we now have flythrough videos of 2 CPE stations at Punggol & Riviera. We can expect that the video for the last CPE station - Elias - should be released some time soon as well.

This is a blog-only post.

Sunday, July 16, 2023

CRL1 & CPE - Official Telegram Channels

 


Telegram groups have become the new means through which the Land Transport Authority (LTA) has digitised its outreach to stakeholders with new rail projects. The messaging platform has been used as a uni-directional channel through which circulars and updates on the various construction contracts are pushed out to residents, businesses and commuters in the area where construction works are taking place. The first wide-spread adoption was undertaken by the Circle Line Stage 6 (CCL6) project and subsequently adopted by the Jurong Region Line (JRL) as well. It appears that the Cross Island Line (CRL) is using this as well. We attempt to consolidate the links for you to join the Telegram channels as well, which have been rolled out for CRL1 and CPE sections, for which all civil contracts have been awarded thus far. It is assumed that the same will follow for CRL2 once the contracts have been awarded and for CRL3 in due time as well.

Saturday, June 24, 2023

P105 - Punggol interchange roadshow

 

24 June 2023 - Renders of new entrances to be added north of Punggol Central.

The Land Transport Authority (LTA) & contractor for contract P105, Woh Hup, is holding a roadshow exhibition at Punggol station today. Situated next to Exit A, it is right where the station connects to Waterway Point mall. If you're in the vicinity, they're there till 8pm today, so there's still time to head on down and check out the exhibit. You might be able to get a magnet souvenir as well, provided that there's still stock available.

Details of the roadshow exhibition for contract P105.


Friday, May 12, 2023

P105 - Punggol Q2 2023 pre-construction update

 

Information on Punggol CPE station by Minister Janil Puthucheary

New posts from Minister Janil Putucheary, MP for the Punggol area, indicate that works for Punggol station on the Cross Island Line - Punggol Extension (CPE) are due to begin this month. Work will commence for setting up the contract P105 site office and CPE Project Information Centre (PIC) that will be located next to My First Skool some time this month. Next month, hoarding will go up for several sites along Punggol Central as well.

Wednesday, January 4, 2023

P105 - Punggol pre-construction

 

2 January 2023 - A view of the existing Punggol MRT & LRT station.

It has been about a month since contract P105 for the construction of Punggol station & over run tunnels has been awarded now. Advanced utility works are ongoing in the areas surrounding the station and are due to be completed by Q3 this year. We take a look at the area before heavy construction work commences and alters the area drastically.

Monday, December 5, 2022

Contract awards - P105 & CR202

 

Render of Punggol Cross Island Line platform.
Source: LTA

A render of one of the facility buildings en route.
Source: LTA

The Land Transport Authority (LTA) announced the award of 2 contracts for the Cross Island Line (CRL) today - contracts P105 & CR202. Contract P105 is for the construction of Punggol interchange station along the Cross Island Line - Punggol Extension (CPE) route. This contract was awarded to local company Woh Hup that had previously constructed Woodlands South station on the Thomson-East Coast Line (TEL) and is now working on Tanjong Katong & Bayshore stations (do head on down to the ERL Construction Blog to see upcoming updates on these stations).

Thursday, May 13, 2021

CPE - Pre-qualification begins

Renders of the CPE stations
Source: Zaobao SG

Recently the Land Transport Authority (LTA) launched pre-qualifications for the Cross Island Line Punggol Extension (CPE) - a 7.3km extension from Pasir Ris to Punggol. The extension will add 3 additional stations to the line with all 3 new stations seemingly featuring side platform configurations There will also be 3 civil contracts for the extension as well - P102, P103 & P105.