This page documents details relating to the TBMs handled by tunnel-only contracts.
For TBMs part of station contracts, please refer to the respective station pages (refer to the Pages section on the sidebar).
CRL Phase 1
Contract CR102
Scope: Construction of 5 twin bored tunnels between Changi East Industrial Zone (CEIZ), Changi East Depot & Aviation Park station
- Main line tunnel (Eastbound between Aviation Park station & CEIZ)
- Main line tunnel (Westbound between Aviation Park station & CEIZ)
- Reception track 1 (Between Aviation Park station & Changi East depot)
- Reception track 2 (Between Aviation Park station & Changi East depot)
- Reception track 3 (Between CEIZ & Changi East depot)
Contractor: Shanghai Tunnel Engineering Co
TBM facts
- 4 Earth Pressure Balance machines would be used
- 1 machine will be used for 2 drives (RT3 & RT2)
- The remaining 3 machines will be used for single drives
- 2 machines will be launched from CEIZ shaft towards AVP station
- 1 machine will be launched from CEIZ shaft towards CE Depot shaft
- 2 machines will be launched CE Depot shaft towards AVP station
- Ultimately, all 4 machines will dock at AVP station
Contract CR105
Contractor: Taisei - China State Construction Engineering Co joint venture
TBM Facts
Number used - 1
Type of machine - Mix shield
Machine diameter - 12.66m
Contract CR110
Scope: Construction of single large diameter bored tunnel from Facility Building 3 to Defu station
Contractor: Nishimatsu Construction
TBM Facts
Number of machines - 1
Type of machine - Earth pressure balance
Machine diameter - 12m
CRL Phase 2
Contract CR202
Scope: Construction of single large diameter bored tunnel connecting Turf City and Bright Hill stations
Contractor: Shanghai Tunnel Engineering Co - Obayashi joint venture
TBM Facts
Number of machines - 1
Type of machine - Slurry (mix shield)
Diameter of machine - 12.69m
![]() |
Herrenknecht mix shield machine number S-1345. Machine's diameter is 12.6m. |
Contract CR207
Scope: Construction of twin bored tunnels between Clementi & Maju stations from intermediate launch shaft.
Contractor: Sinohydro
TBM Facts
Number of machines - 3
Contract CR210
Scope: Construction of twin bored tunnels between Jurong Lake District & West Coast station.
Contractor: Nishimatsu Construction - Okumura
TBM Facts
Number of machines - 2
Trivia