Overview of CRL1 works under contracts CR106 - CR117 as at July 2025.
Top (L - R): CR106 - Loyang, CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris, CR6 - Tampines North
Middle (L - R): CR110 – Large diameter tunnel, CR7 - Defu, CR8 - Hougang, CR9 - Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill

There's a fair bit to update in this snapshot of the Cross Island Line (CRL) for July 2025. This update will mainly focus on progress along phase 1 of the line, the section with the most progress thus far due to the section's earlier announcement, contract award and commencement in general. Nonetheless, tunneling is also underway across all announced phases thus far, so we will touch a little on the progress made on that front thus far. All this & more after the jump.