Sunday, May 31, 2026

CR151 - The first train arrives

Today, the Land Transport Authority (LTA) announced that the first Cross Island Line (CRL) trainset under contract CR151 had reached Singapore's shores. Upon arrival, the train will be transported to the Singapore Rail Test Centre (SRTC) in Tuas for testing & integration works. Similar tests were conducted there for the Circle Line (CCL)'s new batch of third generation trains under contract 851E. Did you manage to catch some of the details from the video that LTA put up? Here's what SGMC has uncovered after a closer look (after the jump).

Friday, May 8, 2026

CRL1 - A snapshot in April 2026

Overview of CRL1 stations CR4 - CR5 & CR8 - CR11 as at April 2026.
Top (L - R): CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris,
Middle (L - R): CR8 - Hougang, CR9 - Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio

Last week, we took a look at the progress of the Cross Island Line (CRL)'s Punggol Extension. This week, we catch up on progress along CRL's phase 1 section, covering 6 contracts under the phase. Join us as we take a look at progress made from Pasir Ris East to Ang Mo Kio in this snapshot update of CRL1.