Tuesday, June 20, 2023

CR111 - Defu update Q2 2023

 

15 June 2023 - An aerial view of preparations for road diversions along Tampines Road.

Contract CR111 for the construction of Defu station and associated tunnels was won by the joint venture of Gamuda & Wai Fong. The contract will involve the completion of the Defu station located underneath Tampines Road and twin bored tunnels to Hougang station, the next stop westwards. As contract CR111 was one of the later awarded contracts for the Cross Island Line (CRL), works have been focused on site preparation till recently.

Wednesday, June 14, 2023

CR151 - Contract awarded for 44 electric trains

 

Render of the CR151 train awarded to CRRC Qingdao Sifang.
Source: LTA

Today, the Land Transport Authority (LTA) announced the award of contract CR151 for 44 train sets to CRRC Qingdao Sifang. The contract also includes an option to purchase 11 further train sets. Initially formed of 6 carriages, the trains can be further lengthened to 8 carriages in the future. Here are some of the features unique to the Cross Island Line (CRL) trains:

  • Starting capacity with 6-cars per train set
  • Future scalability to 8-cars per train set
  • Powered via an overhead catenary rail (OCR) - essentially a third rail but affixed to the tunnel roof and capable of transmitting higher voltage
  • Wider carriage-to-carriage gangways than available on currently existing trains at 1.6m instead of 1.4m
We had previously posted an image from a presentation showing the large diameter single bored tunnel which showed the inclusion of OCR support equipment within the tunnel. In addition, early renders of the Changi East depot also showed the presence of OCR masts within the depot area.

CR116 - Ang Mo Kio update Q2 2023

 

10 June 2023 - Construction of the capping beam for the launch shaft.

Contractor Gammon is not new to the Ang Mo Kio area, having completed the nearby Mayflower station on the Thomson-East Coast Line along Ang Mo Kio Avenue 4 several years back. For the Cross Island Line (CRL), the contractor is back & teaming up with veteran Bachy Soletanche to undertake contract CR116 for the construction of Ang Mo Kio station and tunnels connecting to Teck Ghee station to the west. Quarter 2 of 2023 has been a busy period for the contractor with works ongoing to prepare the site for the oncoming structural works necessary to build the station. We'd like to thank our Instagram follower @linhsu88 for providing us with some images to use in this post as well.

Saturday, June 3, 2023

CR112 - The beginning of CRL excavation (Hougang Q2 2023)

 

2 June 2023 - Excavation at the northern end of the site with completed diaphragm walls.

Contract CR112 was one of the first civil contracts awarded for the Cross Island Line (CRL) phase 1. As such, it is also one of the first contracts to have commenced excavation works with a portion at the northern end of the station site having soil removed within an area where diaphragm wall works have completed. Join us as we bring to you an update on work progress as of the second quarter of 2023 at Hougang station.

Sunday, May 21, 2023

CR2016 - Advanced works for CRL2

 

21 May 2023 - The beginning of hoarding along Clementi Road.

21 May 2023 - Hoarding along Clementi Road.

Recently if you've travelled along Clementi Road, especially around the Singapore Institute of Management (SIM) / Singapore University of Social Sciences (SUSS) stretch, you may have noticed green hoarding along the boundary of the road. Ever wondered what the hoarding is for? Could it be that works for the Cross Island Line (CRL) phase 2 are already beginning? Find out more after the jump.

Friday, May 12, 2023

P105 - Punggol Q2 2023 pre-construction update

 

Information on Punggol CPE station by Minister Janil Puthucheary

New posts from Minister Janil Putucheary, MP for the Punggol area, indicate that works for Punggol station on the Cross Island Line - Punggol Extension (CPE) are due to begin this month. Work will commence for setting up the contract P105 site office and CPE Project Information Centre (PIC) that will be located next to My First Skool some time this month. Next month, hoarding will go up for several sites along Punggol Central as well.

Monday, May 8, 2023

CR106 - Loyang Q1 2023 update

 

30 March 2023

Under contract CR106, a section of Loyang Avenue between Pasir Ris Drive 3 and Loyang Way was closed on 26 February 2023 to facilitate the construction of Loyang Cross Island Line (CRL) station and a vehicular viaduct on top. Since the closure in late February 2023, the work site has been cleared of trees and heavy equipment had moved in.