Saturday, December 30, 2023

CPE & CRL2 - year-end update 2023

 

The 9 station sites of CPE & CRL2 as of end-2023.

2023 was an eventful year for both the Cross Island Line (CRL)'s Punggol Extension (CPE) & Phase 2 (CRL2) sections with the ground breaking ceremony and contracts being awarded respectively. With the ground breaking ceremony taking place this year, work has began at all 3 station sites under the offshoot branch which connects the main CRL line at Pasir Ris with Punggol - a precursor to the long spoken about Northshore Line which would have eventually connected Punggol and Woodlands. Over at CRL2, contract awarded began, with 3 of the 9  civil contracts awarded through the year. All in all, 2023 has been exciting for the phase 2 stations.

CP2 - Elias [Contract P102]
The last of the 3 civil contracts awarded for the CPE section, site clearing has begun at the contract site. Hoarding had gone up around the area to be cleared earlier this year, with the tree felling works taking place towards the end of the year.


27 December 2022

27 December 2022

27 December 2022

27 December 2022

27 December 2022

17 September 2023

17 September 2023

17 September 2023

17 September 2023

17 September 2023

17 September 2023

17 September 2023

17 September 2023

17 September 2023

19 October 2023

19 October 2023

19 October 2023

19 October 2023

19 October 2023

19 October 2023

19 October 2023

19 October 2023

19 October 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

10 December 2023

CP3 - Riviera [Contract P103]
This contract was the first of the 3 civil contracts awarded for the CPE section. As such, the site has seen numerous changes. An existing pedestrian overhead bridge has since been demolished and replaced with a street level crossing. Road diversions have taken place to allow a work site to be created in the road median.


31 December 2022

31 December 2022

31 December 2022

31 December 2022

31 December 2022

31 December 2022

24 June 2023

19 August 2023

19 August 2023

19 August 2023

19 August 2023

19 August 2023

19 August 2023

19 August 2023

19 August 2023

19 August 2023

19 August 2023

19 August 2023

8 October 2023

8 October 2023

8 October 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

CP4 - Punggol [Contract P105]
The site for the interchange station and terminus of the CPE has been slowly ramping up. Two sites on either side of the existing Punggol station have been hoarded up and machinery stored on site. However apart from this, there is little else visible in terms of works being carried out as yet.


2 January 2023

2 January 2023

2 January 2023

2 January 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

6 May 2023

10 September 2023

10 September 2023

10 September 2023

10 September 2023

10 September 2023

10 September 2023

10 September 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

30 December 2023

CR14 - Turf City [Contract CR203]
The contract for the construction of the future Turf City station has yet to be awarded. As such, there are not many visible differences to the site apart from the vacating of the premises by the tenants. Come 1 January 2024, the site will be closed off to the public.


31 December 2022

31 December 2022

31 December 2022

31 December 2022

31 December 2022

31 December 2022

24 December 2023

24 December 2023

24 December 2023

24 December 2023

24 December 2023

24 December 2023

24 December 2023

24 December 2023

24 December 2023

CR15 - King Albert Park [Contract CR205]
The contract for the station was recently awarded this past year. However work is only expected to commence in the first quarter of next year, thus no changes are noted at the site.


31 December 2022

31 December 2022

31 December 2022

31 December 2022

24 December 2023

24 December 2023

24 December 2023

24 December 2023

24 December 2023

CR16 - Maju [Contract CR206]
While the contract for the construction of the station has yet to be awarded, the advanced works contract is underway. Site clearing has taken place and water pipe relocation works are in progress. As the majority of the work takes place in the road side table, the roadway is not yet affected.


25 December 2022

25 December 2022

21 May 2023

21 May 2023

29 October 2023

29 October 2023

24 December 2023

CR17 - Clementi [Contract CR208]
Demolition of 3 existing residential blocks has taken place through the year before the site is handed over to the contractor that was awarded the contract. The police station has been vacated in the later part of the year as well and the winning contractor will be responsible for the demolition of the police station ahead of construction works.


1 January 2023

1 January 2023

23 July 2023

23 July 2023

23 July 2023

23 July 2023

13 August 2023

13 August 2023

27 August 2023

27 August 2023

27 August 2023

10 September 2023

29 October 2023

2 November 2023

2 November 2023

2 November 2023

18 November 2023

18 November 2023

24 December 2023

24 December 2023

24 December 2023

24 December 2023

CR18 - West Coast [Contract CR209]
With the contract only being recently awarded, there are no changes to the site as yet. The winning contractor will be responsible for the demolition of the vacated Tanglin Secondary School building before construction begins.


1 January 2023

26 December 2023

CR19 - Jurong Lake District [Contract CR211]
The contract for the terminus of the line has yet to be awarded, as such there are no changes to the site at present.


1 January 2023

26 December 2023

2024 will bring more milestones such as the award of the remaining contracts for Phase 2 of the line. In addition, we can expect diaphragm wall works to commence along the Punggol Extension and a ground breaking ceremony to be held for Phase 2. Do stay tuned as we continue bringing you the updates in the coming year. Wishing all our readers a Happy New Year!

This post is also available on Instagram & Facebook.

No comments:

Post a Comment