Sunday, June 3, 2018

Soil Investigation: Clementi

The spread of Soil Investigations within Clementi as of 02 June 2018. The dates represent the dates the boreholes
and/or Soil Investigation works were seen and/or officially completed.
As work on the eastern leg of the Cross Island Line (CRL) ramps up, Soil Investigations along the western leg begins to show patterns of study. As can be observed within Clementi over the period of approximately 2 years, a number of boreholes have surfaced showing a possible route alignment option that has been pursued for further study.



2016.03.03 - Soil Investigation works near the Clementi MRT station

2016.03.03 - A notice reflects the project owner as the Land
Transport Authority (LTA). The project description states Soil
Investigation works from Tuas to Changi.
The first Soil Investigation rig appeared in 2016 a stone's throw away from the existing MRT station on the East West Line. This was the only noticeable Soil Investigation within Clementi till a further borehole was dug right outside the Clementi Neighbourhood Police Centre.

2016.11.13 - Borehole located outside the Clementi Neighbourhood Police Centre.

2016.11.13 - Borehole description outside the Clementi Police Neighbourhood Centre.
As of 2nd June 2018, this borehole has since been removed. However, new boreholes were created in the nearby vicinity to obtain other samples in 2018.

2018.04.13 - Soil Investigation rig in front of the Clementi Neighbourhood Police Centre

2018.04.24 - Resultant borehole
2018.04.07 - Soil Investigation rig next to Clementi Neighbourhood Police Centre along Clementi Avenue 5
2018.05.20 - Soil investigation rig along Clementi Avenue 4 outside the Clementi
Neighbourhood Police Centre

2018.05.22 - The resultant borehole along Clementi Avenue 4.
A string of soil investigation rigs and boreholes were also noted stretching from the Block 379 Carpark along Clementi Avenue 5 through the Clementi Community Centre (CC) to Block 339 along the Ulu Pandan canal.

2018.02.05 - Soil Investigation rig in the block 379 car park along Clementi Avenue 5.

20188.03.10 - Resultant borehole with project owner LTA indicated.

2018.02.05 - Soil Investigation rig next to block 339 along Clementi Avenue 5.

2018.03.10 - Resultant borehole.

2018.03.18 - Soil investigation rig between Clementi CC and block 381 along Clementi
Avenue 5.

2018.03.18 - Soil Investigation rig in front of block 339 along the Ulu Pandan canal.
No borehole marker was left in this location.
From the soil investigations, it is likely that the Clementi interchange station will be sited along Clementi Avenue 4. A cluster of exits may be located near the junction of Clementi Avenue 4 and 5 with the line cutting through Clementi CC to run northwards to its next station.