Our last summary update for phase 2 of the Cross Island Line (CRL) was some time ago. With the recent public holidays in the previous month, we managed to make a few visits to some of the sites along the southern section of this line. Do check out the updates to find out more on the progress of the contracts thus far after the jump!
Cross Island Line Construction
Thursday, February 6, 2025
Wednesday, February 5, 2025
CR112 - Hougang updates from Dec 2024 & Jan 2025
![]() |
31 January 2025 - An aerial view of the Hougang station site. |
![]() |
31 January 2025 - An aerial view of the tunneling launch shaft at the northern end of the project. |
It has been some time since we caught up and provided more detailed updates on the construction of some Cross Island Line (CRL) stations. We'll start off with some updates on Hougang, seeing how there has been an increase in activity over the past 2 months with the assembly and subsequent launching of the Tunnel Boring Machines (TBMs) at the station site. More details after the jump!
Thursday, January 2, 2025
CRL1 - TBM Season
![]() |
Contract CR102 TBMs during the assembly phase at the launch shaft. Source: STEC |
A happy new year to all our readers & followers! Recently, we have come across a few new images of tunnel boring machines (TBMs) for the Cross Island Line (CRL) phase 1. Coupled with recent deliveries to sites at Hougang, Ang Mo Kio and Defu, its definitely TBM season for the CRL. What better way to begin the new year than by taking a look at all the machines responsible for building the tunnels for the upcoming CRL1? More of them after the jump.
Saturday, December 14, 2024
CR112 - TBM assemble!
13 December 2024 - The TBM tail shield during lifting operations. |
Contract CR112 has made some headway since the arrival of the Tunnel Boring Machines (TBMs) at the site. Two TBMs will be used to bore the twin tube tunnels towards Serangoon North station. After a public name voting process, the TBMs are to be named Artemis & Valkyrie. Parts of the first TBM were lowered into the launch shaft on 7 December 2024 and the tail shield was lifted in on 13 December 2024.
Monday, December 2, 2024
CR202 - A large TBM for a large tunnel
![]() |
A view of the front of the TBM. Source: Herrenknecht |
Recently, German tunnel boring machine (TBM) manufacturer - Herrenknecht - uploaded several images of the machine numbered S-1365 onto its website. The TBM will be used for contract CR202 to construct the large diameter single bore tunnel through the Central Catchment Nature Reserve, connecting Cross Island Line (CRL)'s phases 1 and 2. The contract, won by a joint venture between Obayashi & Shanghai Tunnel Engineering Co, was the first of several CRL2 contracts to be awarded.
Friday, November 15, 2024
CR108, CR115 & CR205 - Traffic diversions & temporary road closures
![]() |
A compilation of diagrams detailing upcoming road diversions, temporary road closures & changes to the road networks over the weekend of 16 & 17 November near 3 CRL work sites. |
The weekend of 16 & 17 November will be a busy one for the Cross Island Line (CRL) with various traffic diversions, temporary road closures & changes to road schemes taking place across three different projects over 2 phases of the line. The works in particular will affect residents in Pasir Ris at the site of contract CR108, in Ang Mo Kio near site CR115 at Tavistock station and at King Albert Park at the site of CR205.
Monday, November 11, 2024
CR211 - Further information
![]() |
A screenshot from the webinar, showing Jurong Lake District station's Exit 3 design. |
A recent webinar held online by the Bentley to market building information modeling software Synchro allowed viewers to obtain some additional information on Jurong Lake District station under contract CR211. The Cross Island Line (CRL) phase 2 station will be built with an initial 3 exits and two cut & cover tunnel sections on either side of the station. These are known as the Western Cut & Cover Tunnel (WCCT) and Eastern Cut & Cover Tunnel (ECCT).