Phase 2 of the Cross Island Line (CRL) is fast approaching road diversion season. In fact, this section of the line may have already crossed the threshold into the road diversion territory, with the first major diversion having taken place at the Maju station site. Nonetheless, other sites are likewise gearing up for their diversion-eras as well. Which sites are these and which roads will be diverted? Find out all that & more after the jump!
Thursday, March 26, 2026
Monday, July 7, 2025
CRL2 Groundbreaking ceremony
![]() |
| 7 July 2025 - A group photo with contractors of CRL2. |
Today, the Land Transport Authority (LTA) held a groundbreaking ceremony to mark the official commencement of construction on phase 2 of the Cross Island Line (CRL). Connecting 6 stations over 15km of track, the section of line will see the expansion of Singapore's rail network reach areas in the west currently not well covered by the system. Notably, the future housing estate on the site of the former turf club will be served by the MRT and residents at West Coast will have a station to call their own. Also standing to benefit, students at the Singapore University of Social Sciences (SUSS) and Singapore Institute of Management (SIM) will be served by the upcoming Maju station. Stations along this section of the line are Turf City, King Albert Park, Maju, Clementi, West Coast and Jurong Lake District. King Albert Park and Clementi stations will connect to the existing Downtown and East-West lines respectively, allowing convenient transfers for commuters.
Early works under the 9 contracts that make up phase 2 have already commenced, thus today's ceremony is more symbolic in nature. Some of the works that have begun include the demolition of existing structures at the project sites, utility diversions and construction of diaphragm walls for sections where excavation works will be required. The 9 contracts consist of 3 contracts for tunneling between stations and 6 contracts for the construction of stations, some which also include the construction of connecting tunnels.
A total of 11 tunnel boring machines (TBMs) will be required to complete tunneling works along this section of the line, one of which is already busy at work under contract CR202. TBM Jane, launched in May 2025, is a large diameter TBM that will construct the tunnels connecting Turf City station with Bright Hill station on phase 1 of the line. This tunnel will undercross the Central Catchment Nature Reserve (CCNR) without disturbing the surface, a decision that was not undertaken lightly when the line was first planned. Due to concerns from nature groups and other communities, studies were initiated to weigh the benefits of pursuing the direct route over an alternative route avoiding the CCNR entirely. Ultimately, following the studies conducted, the direct route through the CCNR was selected, albeit with some adjustments to the work areas to mitigate impact to the flora and fauna found within the reserve.
In addition to the symbolic start of construction along the second phase, the Minister for Transport - Mr. Jeffrey Siow - also officiated the opening of the phase's Project Information Centre (PIC). Located in Clementi and next to the project site, the PIC serves to allow the community to learn more about the project and its development. On display is a model of the upcoming Clementi station and exhibits of the contracts under this phase of the line. Similar PICs exist in Hougang for Phase 1 of the line and in Punggol for the Punggol extension section.
![]() |
| 7 July 2025 - Opening plaque |
The PIC will be open to the public from 8 July 2025. Operating hours will be 9.00am to 5.00pm, Monday to Friday. Walk-ins are allowed, but booking an appointment through a link to be released is encouraged.
We look forward to the continued progress along CRL2 with the phase officially underway. May the project be completed safely & in a timely manner.
Thursday, February 6, 2025
CRL2 - A snapshot in January 2025
Our last summary update for phase 2 of the Cross Island Line (CRL) was some time ago. With the recent public holidays in the previous month, we managed to make a few visits to some of the sites along the southern section of this line. Do check out the updates to find out more on the progress of the contracts thus far after the jump!
Tuesday, June 25, 2024
CR209 - Demolition of Tanglin Secondary School building
| 16 June 2024 - An aerial view of the station site currently occupied by the former Tanglin Secondary School buildings. |
Contract CR209 for the construction of West Coast station and tunnels connecting to Clementi station was the fourth civil contract awarded for phase 2 of the Cross Island Line (CRL2), following the awards for the large diameter single bored tunnel across the Central Catchment Nature Reserve (contract CR202), King Albert Park station (contract CR205) and Clementi station (contract CR208). Together with the latter two, work was anticipated to begin in Q1 2024. The initial works that began last quarter were site preparation works, such as pre-condition surveys of surrounding buildings and capturing drone footage before any work began proper.
Thursday, March 21, 2024
CR209 - West Coast gearing up
![]() |
| 24 February 2024 - An aerial view of the former Tanglin Secondary School campus. |
As with other Cross Island Line (CRL) phase 2 contracts awarded in 2023, works are ramping up ahead of the area undergoing massive changes at West Coast station site. Currently still occupied by the former Tanglin Secondary School, which moved out after a final year on the campus, the contract will see the demolition of the existing buildings before construction can commence.
Wednesday, December 6, 2023
CRL2 - Contract award for CR209
![]() |
| A render of one of the station exits - likely Exit 2. Source: LTA |
![]() |
| A render of the station's interior. Source: LTA |
Today, the Land Transport Authority (LTA) announced the award of contract CR209 for the construction of West Coast station & associated tunnels under the Cross Island Line phase 2. Contract CR209 is the fourth contract under phase 2 to be awarded - the other contract being contract CR202 for the large diameter tunnel through the Central Catchment Nature Reserve and contracts CR205 and CR208 for the construction of King Albert Park and Clementi interchange stations only respectively.
Monday, July 24, 2023
CRL2 - Release of contract CR203 for Turf City
![]() |
| 24 July 2023 - Tender for contract CR203 Source: LTA |
Today, the Land Transport Authority (LTA) floated the tender for contract CR203. This contract involves the construction of Turf City station and associated tunnels connecting to King Albert Park station in neighbouring contract CR205. Contract CR203 is the sixth contract floated for tender under the Cross Island Line's (CRL) phase 2 which continues the line from Bright Hill to Jurong Lake District. CRL2 is due to commence operations in 2032.
To date, of the contracts floated for tenders, 1 has been awarded, 3 have been closed for evaluation of tender bids & 2 remain open. We've done up a table for ease of reference.
|
Contract
Number |
Status |
Bidders |
|
CR202 |
Awarded |
Obayashi –
STEC JV (Successful) |
|
CR203 |
Open |
Pending –
closing 22 Dec 2023 |
|
CR205 |
Closed for
evaluation |
1. China
Communications Construction Co. Ltd 2. Gammon
Construction & Engineering Pte Ltd 3. Lum Chang
Building Contractors Pte Ltd 4. Ssangyong
Engineering & Construction Co. Ltd |
|
CR206 |
Open |
Pending –
closing 31 July 2023 |
|
CR208 |
Closed for
evaluation |
1. CES_SDC
Pte Ltd 2. China
Communications Construction Co. Ltd 3. Daelim
Engineering & Construction Co Ltd. 4. Sato Kogyo
(S) Pte Ltd |
|
CR209 |
Closed for
evaluation |
1. CES_SDC
Pte Ltd 2. China
Jingye Engineering Corporation Ltd 3. China
Railway First Group Co. Ltd 4. Gamuda
Berhad 5. Shanghai
Tunnel Engineering Co Pte Ltd (STEC) |
With the latest tender floated, the contracts for 5 of the 6 stations along CRL2 have been successfully tendered. The remaining contract for Jurong Lake District station has yet to be floated, along with 2 other contracts - likely to be contracts for tunneling works. The remaining contracts are numbered CR207, CR210 & CR211.
Tuesday, February 14, 2023
West Coast pre-construction
![]() |
| 18 December 2022 - An aerial view of the site of the future West Coast station. |
Before there is any station at West Coast, before there is any construction work, there is a small sleepy neighbourhood. The site of the future West Coast station on the second phase of the Cross Island Line (CRL) is currently occupied by Tanglin Secondary School. A school with a long history dating back to 1964, the school moved into its current premises in 1993 - approximately 30 years ago! In 2016, the school merged with the former Clementi Woods Secondary School (itself a merger between Ghim Moh Secondary & Jin Tai Secondary schools). This year, the school will undergo another merger, this time with New Town Secondary School, that allows the land upon which the school building sits to be freed up for new uses - including that of being home to an MRT station in future.
Monday, December 19, 2022
CR209 - For West Coast station
Thursday, October 13, 2022
CRL2 - Some renders & EIS reports
![]() |
| A render of an exit of Turf City station. Source: LTA |
The Land Transport Authority (LTA) has recently published the Environmental Impact Study (EIS) reports on their website. Within the reports were a few renders of Turf City and King Albert Park stations. Other details were also unveiled within the reports, such as the stations at Maju & Turf City potentially having cripple sidings integrated into the stations and a future knock out panel being provisioned for a "paid link" at Maju station. A heritage study report by the Urban Redevelopment Authority did not yield any other results.
Thursday, September 22, 2022
CRL2 - The next steps
Tuesday, September 20, 2022
CRL2 Announced
![]() |
| 20 September 2022 - Photo taking at the ministerial visit to the East Coast depot. |
CHANGI SOUTH, SINGAPORE - On 20th September, the Land Transport Authority (LTA) unveiled the second phase of the hotly anticipated Cross Island Line (CRL). CRL2 will span 15km, connecting to the first phase at Bright Hill and ending at the Jurong Lake District. Along the way, the line crosses with the Downtown Line (DTL) & East-West Line (EWL), offering commuters an alternative route between the east and west.
Tuesday, September 6, 2022
CRL2 - What's next?
| Overview of the stages in the development of a Rapid Transit System. |
With works on phase 1 of the Cross Island Line (CRL) mostly under way, the next hotly anticipated development for the line will be the announcement of station locations along the phase 2 section. Join us as we explore some of the key milestones to hit before construction works can commence.
Friday, August 5, 2022
CRL2 - Speculated Station Locations
![]() |
| A map of the expected phase 2 of the Cross Island Line. Own production. |
![]() |
| The Urban Redevelopment Authority (URA) Long-Term Plan. Source: URA |
![]() |
| Geographical map of our expected CRL2 stations & alignment based on URA's long term plan. |
Monday, June 27, 2022
CRL2 - Pre-qualification begins
![]() |
| Screen capture of pre-qualification for CRL2 contracts |
Pre-qualification for 8 contracts along the Cross Island Line (CRL) phase 2 has begun. Details of the pre-qualification for the contracts was released on 31 May 2022. With an expected closure date of 28 June 2022, it is highly likely that the stations along this section of the line will be officially announced this year.
Wednesday, February 27, 2019
CRL2 - Advanced Engineering studies
![]() |
| Screenshot of tenders for Advanced Engineering studies for CRL2 |
Both contracts are expected to be delivered by 30 September 2022.








.jpeg)