Showing posts with label CR211. Show all posts
Showing posts with label CR211. Show all posts

Sunday, September 13, 2026

CRL - A snapshot in August 2026

Overview of CRL stations and contracts as at August 2026.
Top (L - R): NE14 - Hougang interchange, NS16 - Ang Mo Kio interchange
Middle (L - R): CP3 - Riviera, CP4 - Punggol
Bottom (L - R): Contract CR210 - Twin bored tunnels, CR19 - Jurong Lake District


Just a quick update for August, as time really does not seem to be on our side this year. Nonetheless, we've managed to spread our coverage over the various phases of the line - a little bit here and a little bit there. In this snapshot update, we cover some of the key observations across the line from existing interchange station modification works to tunnel progress. More after the jump!

Saturday, August 8, 2026

CRL - A snapshot in July 2026

A compilation of the various sites across Phases 1 and 2 in July 2026.

With the announcement of the Cross Island Line (CRL)'s final phase on 31 July 2026, we now know that the line will stretch for 67km, making this line the longest in the country - beating out the East-West Line (EWL)'s record of 54km by a fair bit. This means that the CRL is a really big project, spanning end-to-end across the entire country. While the EWL also crosses the island from east to west, it mostly sticks to the southern section of the island. In comparison, the CRL swings further north and south than the EWL, making its route much more varied and spread out. This translates into it being much more difficult to easily visit and keep track of all contract sites.

For this update, we tried to cover as much ground as we could to give you an idea of where the line stands in progress. As phase 3 was only announced right at the end of the month, we won't be yet including that section in this update. Nonetheless, all the previous phases of the line that were officially announced are covered in this update in some way, form or manner. There's a lot to unpack, so jump right on in after the jump.

Thursday, March 26, 2026

CRL2 - A snapshot in March 2026

Overview of CRL2 stations CR19 - CR15 & contract CR210 & CR207 sites as at March 2026.
Top (L - R): CR19 - Jurong Lake District, CR210 launch shaft
Middle (L - R): CR18 - West Coast, CR17 - Clementi, CR207 launch shaft
Bottom (L - R): CR16 - Maju, CR15 - King Albert Park

Phase 2 of the Cross Island Line (CRL) is fast approaching road diversion season. In fact, this section of the line may have already crossed the threshold into the road diversion territory, with the first major diversion having taken place at the Maju station site. Nonetheless, other sites are likewise gearing up for their diversion-eras as well. Which sites are these and which roads will be diverted? Find out all that & more after the jump!

Saturday, November 1, 2025

CRL - A snapshot in October 2025

Overview of CRL1 stations CR4 - CR12 as at October 2025.
Top (L - R): CR4 – Pasir Ris East, CR5/CP1 – Pasir Ris, CR6 – Tampines North
Middle (L - R): CR7 – Defu, CR8 – Hougang, CR9 – Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR12 – Teck Ghee


Overview of CPE stations CP2 - CP4 & CRL2 stations CR16 - CR19 as at October 2025.
Top (L - R): CP2 – Elias, CP3 – Riviera, CP4 – Punggol
Middle (L - R): CR16 – Maju, CR207 – Twin bored tunnels, CR17 – Clementi
Bottom (L - R): CR18 – West Coast, CR210 – Twin bored tunnels, CR19 – Jurong Lake District

It's been a while since we've done such an extensive coverage of the Cross Island Line (CRL) across its three current phases that have been announced thus far, hence we thought we'd let October be our month of diversity. Updates for this month stretch from Pasir Ris East all the way to Punggol & Jurong Lake District. If you've been curious on how things were progressing, this post is for you. Do be ready, this update's kind of MEGA.

Saturday, September 13, 2025

CRL - A snapshot in August 2025

Overview of CRL1 stations CR3 - CR10 as at August 2025.
Top (L - R): CR3 - Loyang, CR4 - Pasir Ris East
Middle (L - R): CR5/CP1 - Pasir Ris, CR8 - Hougang
Bottom (L - R): CR9 - Serangoon North, CR10 – Tavistock


Overview of CRL1 station CR11 & CRL2 stations CR17 - CR19 as at August 2025.
Top (L - R): CR11 – Ang Mo Kio, CR207 - Launch shaft
Middle (L - R): CR17 - Clementi, CR18 - West Coast
Bottom (L - R): CR210 - Launch shaft, CR19 - Jurong Lake District

Roughly about three-quarters into the year, how has progress been along the Cross Island Line? We take a closer look at some of the key sites along the line in both phases 1 and 2 in this August look-back.

Monday, July 7, 2025

CRL2 Groundbreaking ceremony

7 July 2025 - A group photo with contractors of CRL2.

Today, the Land Transport Authority (LTA) held a groundbreaking ceremony to mark the official commencement of construction on phase 2 of the Cross Island Line (CRL). Connecting 6 stations over 15km of track, the section of line will see the expansion of Singapore's rail network reach areas in the west currently not well covered by the system. Notably, the future housing estate on the site of the former turf club will be served by the MRT and residents at West Coast will have a station to call their own. Also standing to benefit, students at the Singapore University of Social Sciences (SUSS) and Singapore Institute of Management (SIM) will be served by the upcoming Maju station. Stations along this section of the line are Turf City, King Albert Park, Maju, Clementi, West Coast and Jurong Lake District. King Albert Park and Clementi stations will connect to the existing Downtown and East-West lines respectively, allowing convenient transfers for commuters.

Early works under the 9 contracts that make up phase 2 have already commenced, thus today's ceremony is more symbolic in nature. Some of the works that have begun include the demolition of existing structures at the project sites, utility diversions and construction of diaphragm walls for sections where excavation works will be required. The 9 contracts consist of 3 contracts for tunneling between stations and 6 contracts for the construction of stations, some which also include the construction of connecting tunnels.

A total of 11 tunnel boring machines (TBMs) will be required to complete tunneling works along this section of the line, one of which is already busy at work under contract CR202. TBM Jane, launched in May 2025, is a large diameter TBM that will construct the tunnels connecting Turf City station with Bright Hill station on phase 1 of the line. This tunnel will undercross the Central Catchment Nature Reserve (CCNR) without disturbing the surface, a decision that was not undertaken lightly when the line was first planned. Due to concerns from nature groups and other communities, studies were initiated to weigh the benefits of pursuing the direct route over an alternative route avoiding the CCNR entirely. Ultimately, following the studies conducted, the direct route through the CCNR was selected, albeit with some adjustments to the work areas to mitigate impact to the flora and fauna found within the reserve.

In addition to the symbolic start of construction along the second phase, the Minister for Transport - Mr. Jeffrey Siow - also officiated the opening of the phase's Project Information Centre (PIC). Located in Clementi and next to the project site, the PIC serves to allow the community to learn more about the project and its development. On display is a model of the upcoming Clementi station and exhibits of the contracts under this phase of the line. Similar PICs exist in Hougang for Phase 1 of the line and in Punggol for the Punggol extension section.

7 July 2025 - Opening plaque

The PIC will be open to the public from 8 July 2025. Operating hours will be 9.00am to 5.00pm, Monday to Friday. Walk-ins are allowed, but booking an appointment through a link to be released is encouraged.

We look forward to the continued progress along CRL2 with the phase officially underway. May the project be completed safely & in a timely manner.

Sunday, June 8, 2025

CRL - A snapshot in May 2025

An overview of CRL1 contracts CR101 - CR111 as of May 2025.
Top (L - R) : CR101 - Changi East Depot, CR102 - Tunnels, CR103 - Aviation Park station
Middle (L - R) : CR106 - Loyang station, CR107 - Pasir Ris East station, CR108 - Pasir Ris station
Bottom (L - R) : CR109 - Tampines North station, CR110 - Large bored tunnel, CR111 - Defu station

An overview of CRL1 contracts CR112 - CR117, CPE contracts P102 & P103 and CRL2 contract CR202 as of May 2025.
Top (L - R) : CR112 - Hougang station, CR113 - Serangoon North station, CR115 - Tavistock station
Middle (L - R) : CR116 - Ang Mo Kio station, N109A - Teck Ghee station, CR117 - Bright Hill station
Bottom (L - R) : P102 - Elias station, P103 - Cripple siding, CR202 - Large bored tunnel

An overview of CRL2 contracts CR205 - CR211 as of May 2025.
Top (L - R) : CR205 - King Albert Park station, CR206 - Maju station
Middle (L - R) : CR207 - Tunnels, CR208 - Clementi station, CR209 - West Coast station
Bottom (L - R) : CR210 - Tunnels, CR211 - Jurong Lake District station

It has been a while since we've done a snapshot feature of the Cross Island Line (CRL), with our last being done in February for the Punggol Extension. Part of this stems for the works being "less noticeable", since the majority of this takes place underground and relatively out of sight. Another part is that it also appears that updates on the CRL aren't as popular compared to updates on other lines (granted, the above ground line updates are A LOT more interesting as you actually see things change with most monthly updates). Nonetheless, we thought it's time to see where the CRL is in progress with this rather comprehensive mid-year update.

Thursday, February 6, 2025

CRL2 - A snapshot in January 2025

A view of the various contract sites for Cross Island Line phase 2 in January 2025.
Top: Contract CR207 along Clementi Road
Middle (L - R): CR17 - Clementi station, CR18 - West Coast station
Bottom (L - R): Contract CR210 site near Jurong Town Hall station, CR19 - Jurong Lake District

Our last summary update for phase 2 of the Cross Island Line (CRL) was some time ago. With the recent public holidays in the previous month, we managed to make a few visits to some of the sites along the southern section of this line. Do check out the updates to find out more on the progress of the contracts thus far after the jump!

Monday, November 11, 2024

CR211 - Further information

A screenshot from the webinar, showing Jurong Lake District station's Exit 3 design.

A recent webinar held online by the Bentley to market building information modeling software Synchro allowed viewers to obtain some additional information on Jurong Lake District station under contract CR211. The Cross Island Line (CRL) phase 2 station will be built with an initial 3 exits and two cut & cover tunnel sections on either side of the station. These are known as the Western Cut & Cover Tunnel (WCCT) and Eastern Cut & Cover Tunnel (ECCT).

Thursday, September 26, 2024

CR211 - Telegram channel launch, CR115 - TBM launch & CR112 - TBMs named

 

A render of the Jurong Lake District station being built under contract CR211.
Source: LTA

20 September 2024 - The launching ceremony for tunneling under contract CR115.
Source: LinkedIn

Tunnel boring machines for contract CR112.
Source: Forms.sg

We have a quick update on some developments along the Cross Island Line (CRL) to share: The launch of contract CR211's Telegram channel & TBM #1 for contract CR115 and confirmed names of the tunnel boring machines (TBMs) for contract CR112. More information after the jump.

Saturday, August 3, 2024

CRL - A snapshot in July 2024

Overview of CRL1 contracts CR102 - CR115 as of July 2024.
Top (L - R):  CR102 - Tunnels at Changi East, CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris
Middle (L - R): CR6 - Tampines North, CR110 – Large diameter tunnel, CR7 - Defu
Bottom (L - R): CR8 - Hougang, CR9 - Serangoon North, CR10 – Tavistock 


Overview of CRL1 contracts CR116 & N109A, CPE contracts P102 - P103 & CRL2 contracts
CR205 - CR211 as at July 2024.
Top (L - R): CR11 - Ang Mo Kio, CR12 - Teck Ghee, CP2 - Elias
Middle (L - R): P103 Cripple siding, CR15 - King Albert Park, CR16 - Maju
Bottom (L - R): CR17 - Clementi, CR18 - West Coast, CR19 - Jurong Lake District

July was a momentous month for the Cross Island Line (CRL). All civil contracts for the construction of stations across phases 1, 2 and the Punggol extension were awarded. Along phase 1, several contracts were in the midst of Tunnel Boring Machine (TBM) assembly and subsequent launch as well. In this update, we take a brief look at the progress made across the line's first few phases.

Wednesday, July 31, 2024

CRL2 - Contract CR211 awarded

 

A render of one of the station's three exits.
Source: LTA

A render of the station's concourse level.
Source: LTA

The Land Transport Authority (LTA) today announced the award of contract CR211 for the construction of Jurong Lake District and cut & cover tunnels on either end of the station to KTC Civil Engineering & Construction Pte Ltd. The contractor is also responsible for Maju station on the Cross Island Line (CRL)'s phase 2 as well, under contract CR206. KTC successfully beat out 6 other contractors that bid for the contract, including 1 that was not shortlisted.

Friday, April 5, 2024

CRL - A snapshot in March 2024

Overview of CRL1 stations CR4 - CR13 as at March 2024.
Top (L - R): CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris, CR7 - Defu
Middle (L - R): CR8 - Hougang, CR9 - Serangoon North, CR10 - Tavistock
Bottom (L - R): CR11 – Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill


Overview of CPE & CRL2 stations CP2 - CP4 & CR14 - CR19 as at March 2024.
Top (L - R): CP2 - Elias, CP3 - Riviera, CP4 - Punggol
Middle (L - R): CR14 - Turf City, CR15 - King Albert Park, CR16 - Maju
Bottom (L - R): CR17 - Clementi, CR18 - West Coast, CR19 - Jurong Lake District

It's been a whirlwind first quarter of the year. We take the opportunity to check in on the progress of the various construction sites along the Cross Island Line (CRL)'s various phases in the month of March and provide a glimpse at the progress being made. Do check out the various projects after the jump.

Saturday, December 30, 2023

CPE & CRL2 - year-end update 2023

 

The 9 station sites of CPE & CRL2 as of end-2023.

2023 was an eventful year for both the Cross Island Line (CRL)'s Punggol Extension (CPE) & Phase 2 (CRL2) sections with the ground breaking ceremony and contracts being awarded respectively. With the ground breaking ceremony taking place this year, work has began at all 3 station sites under the offshoot branch which connects the main CRL line at Pasir Ris with Punggol - a precursor to the long spoken about Northshore Line which would have eventually connected Punggol and Woodlands. Over at CRL2, contract awarded began, with 3 of the 9  civil contracts awarded through the year. All in all, 2023 has been exciting for the phase 2 stations.

Sunday, May 21, 2023

CR2016 - Advanced works for CRL2

 

21 May 2023 - The beginning of hoarding along Clementi Road.

21 May 2023 - Hoarding along Clementi Road.

Recently if you've travelled along Clementi Road, especially around the Singapore Institute of Management (SIM) / Singapore University of Social Sciences (SUSS) stretch, you may have noticed green hoarding along the boundary of the road. Ever wondered what the hoarding is for? Could it be that works for the Cross Island Line (CRL) phase 2 are already beginning? Find out more after the jump.

Tuesday, September 20, 2022

CRL2 Announced

 

20 September 2022 - Photo taking at the ministerial visit to the East Coast depot.

CHANGI SOUTH, SINGAPORE - On 20th September, the Land Transport Authority (LTA) unveiled the second phase of the hotly anticipated Cross Island Line (CRL). CRL2 will span 15km, connecting to the first phase at Bright Hill and ending at the Jurong Lake District. Along the way, the line crosses with the Downtown Line (DTL) & East-West Line (EWL), offering commuters an alternative route between the east and west.

Tuesday, September 6, 2022

CRL2 - What's next?

Overview of the stages in the development of a Rapid Transit System.

With works on phase 1 of the Cross Island Line (CRL) mostly under way, the next hotly anticipated development for the line will be the announcement of station locations along the phase 2 section. Join us as we explore some of the key milestones to hit before construction works can commence.

Friday, August 5, 2022

CRL2 - Speculated Station Locations

A map of the expected phase 2 of the Cross Island Line. Own production.

As it has been more than 2 years since Cross Island Line (CRL) Punggol Extension was announced, we are expecting news of the next phase of the line to be announced this year. With an expected completion date of 2032, we foresee tenders for advanced contracts to be published soon. Earlier in June, pre-qualifications for 8 contracts for the second phase of the line were called for.

The Urban Redevelopment Authority (URA) Long-Term Plan.
Source: URA

The Urban Redevelopment Authority (URA) also published the latest Long-Term Plan in June 2022 which showed the notional full alignment of the CRL. By overlaying the long-term plan map over a geographic map, we were able to collaborate the supporting data and information with the latest sightings of soil investigation works to compile a list of probable station locations for the CRL2 section. This section of the CRL will continue from the tunnel section directly crossing below the Central Catchment Nature Reserve (CCNR), and ends at Jurong Lake District.

We expect that there will be a total of 6 stations in this section, which stretches over 15km consisting of 5km below the CCNR, and 10km of tunnels between the 6 stations.
Geographical map of our expected CRL2 stations & alignment based on URA's long term plan.


Monday, June 27, 2022

CRL2 - Pre-qualification begins

 

Screen capture of pre-qualification for CRL2 contracts

Pre-qualification for 8 contracts along the Cross Island Line (CRL) phase 2 has begun. Details of the pre-qualification for the contracts was released on 31 May 2022. With an expected closure date of 28 June 2022, it is highly likely that the stations along this section of the line will be officially announced this year.