Phase 2 of the Cross Island Line (CRL) is fast approaching road diversion season. In fact, this section of the line may have already crossed the threshold into the road diversion territory, with the first major diversion having taken place at the Maju station site. Nonetheless, other sites are likewise gearing up for their diversion-eras as well. Which sites are these and which roads will be diverted? Find out all that & more after the jump!
Thursday, March 26, 2026
Monday, July 7, 2025
CRL2 Groundbreaking ceremony
![]() |
| 7 July 2025 - A group photo with contractors of CRL2. |
Today, the Land Transport Authority (LTA) held a groundbreaking ceremony to mark the official commencement of construction on phase 2 of the Cross Island Line (CRL). Connecting 6 stations over 15km of track, the section of line will see the expansion of Singapore's rail network reach areas in the west currently not well covered by the system. Notably, the future housing estate on the site of the former turf club will be served by the MRT and residents at West Coast will have a station to call their own. Also standing to benefit, students at the Singapore University of Social Sciences (SUSS) and Singapore Institute of Management (SIM) will be served by the upcoming Maju station. Stations along this section of the line are Turf City, King Albert Park, Maju, Clementi, West Coast and Jurong Lake District. King Albert Park and Clementi stations will connect to the existing Downtown and East-West lines respectively, allowing convenient transfers for commuters.
Early works under the 9 contracts that make up phase 2 have already commenced, thus today's ceremony is more symbolic in nature. Some of the works that have begun include the demolition of existing structures at the project sites, utility diversions and construction of diaphragm walls for sections where excavation works will be required. The 9 contracts consist of 3 contracts for tunneling between stations and 6 contracts for the construction of stations, some which also include the construction of connecting tunnels.
A total of 11 tunnel boring machines (TBMs) will be required to complete tunneling works along this section of the line, one of which is already busy at work under contract CR202. TBM Jane, launched in May 2025, is a large diameter TBM that will construct the tunnels connecting Turf City station with Bright Hill station on phase 1 of the line. This tunnel will undercross the Central Catchment Nature Reserve (CCNR) without disturbing the surface, a decision that was not undertaken lightly when the line was first planned. Due to concerns from nature groups and other communities, studies were initiated to weigh the benefits of pursuing the direct route over an alternative route avoiding the CCNR entirely. Ultimately, following the studies conducted, the direct route through the CCNR was selected, albeit with some adjustments to the work areas to mitigate impact to the flora and fauna found within the reserve.
In addition to the symbolic start of construction along the second phase, the Minister for Transport - Mr. Jeffrey Siow - also officiated the opening of the phase's Project Information Centre (PIC). Located in Clementi and next to the project site, the PIC serves to allow the community to learn more about the project and its development. On display is a model of the upcoming Clementi station and exhibits of the contracts under this phase of the line. Similar PICs exist in Hougang for Phase 1 of the line and in Punggol for the Punggol extension section.
![]() |
| 7 July 2025 - Opening plaque |
The PIC will be open to the public from 8 July 2025. Operating hours will be 9.00am to 5.00pm, Monday to Friday. Walk-ins are allowed, but booking an appointment through a link to be released is encouraged.
We look forward to the continued progress along CRL2 with the phase officially underway. May the project be completed safely & in a timely manner.
Friday, November 15, 2024
CR108, CR115 & CR205 - Traffic diversions & temporary road closures
![]() |
| A compilation of diagrams detailing upcoming road diversions, temporary road closures & changes to the road networks over the weekend of 16 & 17 November near 3 CRL work sites. |
The weekend of 16 & 17 November will be a busy one for the Cross Island Line (CRL) with various traffic diversions, temporary road closures & changes to road schemes taking place across three different projects over 2 phases of the line. The works in particular will affect residents in Pasir Ris at the site of contract CR108, in Ang Mo Kio near site CR115 at Tavistock station and at King Albert Park at the site of CR205.
Wednesday, March 6, 2024
Contract CR205 - King Albert Park kicks off construction
![]() |
| 15 February 2024 - A view of the existing Downtown Line station with the Cross Island Line site seen at the back. |
Contract CR205 for the construction of the Cross Island Line (CRL)'s King Albert Park station was one of the first civil contracts for stations on phase 2 of the line to be awarded. With the successful award of the contract, works were to begin on site by the end of Q1 2024. Although the station site appears to be quiet, a fair bit of work has begun taking place.
Tuesday, January 30, 2024
CR205 - New renders
![]() |
| A render of a street-level structure featuring a wooden finish. Source: LinkedIn |
Recently the team came across 2 new renders of the Cross Island Line's (CRL) King Albert Park station. The renders show the wooden-like finishings of the street level facilities and allows users a closer look in at the station platform area. These new render images come in addition to 3 other previously released images.
Monday, October 2, 2023
CRL2 - Contract awards for CR205 & CR208
![]() |
| A view of the CRL platform at King Albert Park station. Source: LTA |
The second phase of the Cross Island Line (CRL) achieved a milestone today with the award of 2 contracts - CR205 & CR208. The contracts are for the design & construction of King Albert Park and Clementi interchange stations respectively.
Monday, July 24, 2023
CRL2 - Release of contract CR203 for Turf City
![]() |
| 24 July 2023 - Tender for contract CR203 Source: LTA |
Today, the Land Transport Authority (LTA) floated the tender for contract CR203. This contract involves the construction of Turf City station and associated tunnels connecting to King Albert Park station in neighbouring contract CR205. Contract CR203 is the sixth contract floated for tender under the Cross Island Line's (CRL) phase 2 which continues the line from Bright Hill to Jurong Lake District. CRL2 is due to commence operations in 2032.
To date, of the contracts floated for tenders, 1 has been awarded, 3 have been closed for evaluation of tender bids & 2 remain open. We've done up a table for ease of reference.
|
Contract
Number |
Status |
Bidders |
|
CR202 |
Awarded |
Obayashi –
STEC JV (Successful) |
|
CR203 |
Open |
Pending –
closing 22 Dec 2023 |
|
CR205 |
Closed for
evaluation |
1. China
Communications Construction Co. Ltd 2. Gammon
Construction & Engineering Pte Ltd 3. Lum Chang
Building Contractors Pte Ltd 4. Ssangyong
Engineering & Construction Co. Ltd |
|
CR206 |
Open |
Pending –
closing 31 July 2023 |
|
CR208 |
Closed for
evaluation |
1. CES_SDC
Pte Ltd 2. China
Communications Construction Co. Ltd 3. Daelim
Engineering & Construction Co Ltd. 4. Sato Kogyo
(S) Pte Ltd |
|
CR209 |
Closed for
evaluation |
1. CES_SDC
Pte Ltd 2. China
Jingye Engineering Corporation Ltd 3. China
Railway First Group Co. Ltd 4. Gamuda
Berhad 5. Shanghai
Tunnel Engineering Co Pte Ltd (STEC) |
With the latest tender floated, the contracts for 5 of the 6 stations along CRL2 have been successfully tendered. The remaining contract for Jurong Lake District station has yet to be floated, along with 2 other contracts - likely to be contracts for tunneling works. The remaining contracts are numbered CR207, CR210 & CR211.
Wednesday, January 18, 2023
King Albert Park pre-construction 2022
![]() |
| 31 December 2022 - A view eastwards along Dunearn Road |
Not too long ago, King Albert Park was the site of a massive construction attempt underneath Bukit Timah Road. The roadway was diverted atop the canal and construction machinery was busy at work constructing the underground station for the Downtown Line (DTL). Those days now date back almost 8 years ago. But soon, it will be time to do it all again when works commence for the Cross Island Line (CRL). Works this round will be concentrated along Blackmore Drive, however. The team takes a look at the area before all the heavy works commence.
Friday, January 6, 2023
CR205 & CR208 - 2nd pre-qualifications
![]() |
3 January 2023 - Companies that have successfully pre-qualified after the second round for contract CR205. |
![]() |
| 3 January 2023 - Companies that have successfully pre-qualified after the second round for contract CR208. |
Last year, 3 contracts were tendered for the Cross Island Line (CRL) phase 2 for the construction of King Albert Park interchange (contract CR205), Clementi interchange (contract CR208) & West Coast station (contract CR209). Concurrently, the Land Transport Authority (LTA) also launched a second round of pre-qualification for the contracts, for which has since been closed for the former but is still open till 16 January 2023 for the latter.
As the pre-qualification exercise for both contracts CR205 & CR208 have concluded, the list of eligible companies for bidding for the projects has been published on government portal Gebiz. There are 2 companies that can proceed to submit tender bids for contract CR205 and 6 that can submit bids for contract CR208. It will be interesting to see which companies make a final bid for the respective contracts.
We will keep a keen watch on the contract bidding process and provide updates once available.
This post is also available on Instagram.
Wednesday, November 23, 2022
CR205 - For King Albert Park
![]() |
| Contract details as released on Gebiz portal. |
![]() |
| Contract delivery date as seen on Gebiz portal |
Thursday, October 13, 2022
CRL2 - Some renders & EIS reports
![]() |
| A render of an exit of Turf City station. Source: LTA |
The Land Transport Authority (LTA) has recently published the Environmental Impact Study (EIS) reports on their website. Within the reports were a few renders of Turf City and King Albert Park stations. Other details were also unveiled within the reports, such as the stations at Maju & Turf City potentially having cripple sidings integrated into the stations and a future knock out panel being provisioned for a "paid link" at Maju station. A heritage study report by the Urban Redevelopment Authority did not yield any other results.
Thursday, September 22, 2022
CRL2 - The next steps
Tuesday, September 20, 2022
CRL2 Announced
![]() |
| 20 September 2022 - Photo taking at the ministerial visit to the East Coast depot. |
CHANGI SOUTH, SINGAPORE - On 20th September, the Land Transport Authority (LTA) unveiled the second phase of the hotly anticipated Cross Island Line (CRL). CRL2 will span 15km, connecting to the first phase at Bright Hill and ending at the Jurong Lake District. Along the way, the line crosses with the Downtown Line (DTL) & East-West Line (EWL), offering commuters an alternative route between the east and west.
Tuesday, September 6, 2022
CRL2 - What's next?
| Overview of the stages in the development of a Rapid Transit System. |
With works on phase 1 of the Cross Island Line (CRL) mostly under way, the next hotly anticipated development for the line will be the announcement of station locations along the phase 2 section. Join us as we explore some of the key milestones to hit before construction works can commence.
Friday, August 5, 2022
CRL2 - Speculated Station Locations
![]() |
| A map of the expected phase 2 of the Cross Island Line. Own production. |
![]() |
| The Urban Redevelopment Authority (URA) Long-Term Plan. Source: URA |
![]() |
| Geographical map of our expected CRL2 stations & alignment based on URA's long term plan. |
Monday, June 27, 2022
CRL2 - Pre-qualification begins
![]() |
| Screen capture of pre-qualification for CRL2 contracts |
Pre-qualification for 8 contracts along the Cross Island Line (CRL) phase 2 has begun. Details of the pre-qualification for the contracts was released on 31 May 2022. With an expected closure date of 28 June 2022, it is highly likely that the stations along this section of the line will be officially announced this year.
Wednesday, December 1, 2021
LTA Virtual Exhibition - CRL2, CRL3 & CR01 stations
![]() |
| Screenshot from LTA's Virtual Tour Source: LTA |
The Land Transport Authority (LTA) on 1 December 2021 launched its virtual exhibition - titled Connecting People, Places & Possibilities. The exhibition journeys through Singapore's land transport milestones, highlighting key decisions made in the journey thus far.
Wednesday, February 27, 2019
CRL2 - Advanced Engineering studies
![]() |
| Screenshot of tenders for Advanced Engineering studies for CRL2 |
Both contracts are expected to be delivered by 30 September 2022.
Tuesday, June 5, 2018
Soil Investigations: King Albert Park
![]() |
| The spread of soil investigation borehole locations as of 4 June 2018. |























