Saturday, August 8, 2026

CRL - A snapshot in July 2026

A compilation of the various sites across Phases 1 and 2 in July 2026.

With the announcement of the Cross Island Line (CRL)'s final phase on 31 July 2026, we now know that the line will stretch for 67km, making this line the longest in the country - beating out the East-West Line (EWL)'s record of 54km by a fair bit. This means that the CRL is a really big project, spanning end-to-end across the entire country. While the EWL also crosses the island from east to west, it mostly sticks to the southern section of the island. In comparison, the CRL swings further north and south than the EWL, making its route much more varied and spread out. This translates into it being much more difficult to easily visit and keep track of all contract sites.

For this update, we tried to cover as much ground as we could to give you an idea of where the line stands in progress. As phase 3 was only announced right at the end of the month, we won't be yet including that section in this update. Nonetheless, all the previous phases of the line that were officially announced are covered in this update in some way, form or manner. There's a lot to unpack, so jump right on in after the jump.

Thursday, March 26, 2026

CRL2 - A snapshot in March 2026

Overview of CRL2 stations CR19 - CR15 & contract CR210 & CR207 sites as at March 2026.
Top (L - R): CR19 - Jurong Lake District, CR210 launch shaft
Middle (L - R): CR18 - West Coast, CR17 - Clementi, CR207 launch shaft
Bottom (L - R): CR16 - Maju, CR15 - King Albert Park

Phase 2 of the Cross Island Line (CRL) is fast approaching road diversion season. In fact, this section of the line may have already crossed the threshold into the road diversion territory, with the first major diversion having taken place at the Maju station site. Nonetheless, other sites are likewise gearing up for their diversion-eras as well. Which sites are these and which roads will be diverted? Find out all that & more after the jump!

Saturday, November 1, 2025

CRL - A snapshot in October 2025

Overview of CRL1 stations CR4 - CR12 as at October 2025.
Top (L - R): CR4 – Pasir Ris East, CR5/CP1 – Pasir Ris, CR6 – Tampines North
Middle (L - R): CR7 – Defu, CR8 – Hougang, CR9 – Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR12 – Teck Ghee


Overview of CPE stations CP2 - CP4 & CRL2 stations CR16 - CR19 as at October 2025.
Top (L - R): CP2 – Elias, CP3 – Riviera, CP4 – Punggol
Middle (L - R): CR16 – Maju, CR207 – Twin bored tunnels, CR17 – Clementi
Bottom (L - R): CR18 – West Coast, CR210 – Twin bored tunnels, CR19 – Jurong Lake District

It's been a while since we've done such an extensive coverage of the Cross Island Line (CRL) across its three current phases that have been announced thus far, hence we thought we'd let October be our month of diversity. Updates for this month stretch from Pasir Ris East all the way to Punggol & Jurong Lake District. If you've been curious on how things were progressing, this post is for you. Do be ready, this update's kind of MEGA.

Saturday, September 13, 2025

CRL - A snapshot in August 2025

Overview of CRL1 stations CR3 - CR10 as at August 2025.
Top (L - R): CR3 - Loyang, CR4 - Pasir Ris East
Middle (L - R): CR5/CP1 - Pasir Ris, CR8 - Hougang
Bottom (L - R): CR9 - Serangoon North, CR10 – Tavistock


Overview of CRL1 station CR11 & CRL2 stations CR17 - CR19 as at August 2025.
Top (L - R): CR11 – Ang Mo Kio, CR207 - Launch shaft
Middle (L - R): CR17 - Clementi, CR18 - West Coast
Bottom (L - R): CR210 - Launch shaft, CR19 - Jurong Lake District

Roughly about three-quarters into the year, how has progress been along the Cross Island Line? We take a closer look at some of the key sites along the line in both phases 1 and 2 in this August look-back.

Monday, July 7, 2025

CRL2 Groundbreaking ceremony

7 July 2025 - A group photo with contractors of CRL2.

Today, the Land Transport Authority (LTA) held a groundbreaking ceremony to mark the official commencement of construction on phase 2 of the Cross Island Line (CRL). Connecting 6 stations over 15km of track, the section of line will see the expansion of Singapore's rail network reach areas in the west currently not well covered by the system. Notably, the future housing estate on the site of the former turf club will be served by the MRT and residents at West Coast will have a station to call their own. Also standing to benefit, students at the Singapore University of Social Sciences (SUSS) and Singapore Institute of Management (SIM) will be served by the upcoming Maju station. Stations along this section of the line are Turf City, King Albert Park, Maju, Clementi, West Coast and Jurong Lake District. King Albert Park and Clementi stations will connect to the existing Downtown and East-West lines respectively, allowing convenient transfers for commuters.

Early works under the 9 contracts that make up phase 2 have already commenced, thus today's ceremony is more symbolic in nature. Some of the works that have begun include the demolition of existing structures at the project sites, utility diversions and construction of diaphragm walls for sections where excavation works will be required. The 9 contracts consist of 3 contracts for tunneling between stations and 6 contracts for the construction of stations, some which also include the construction of connecting tunnels.

A total of 11 tunnel boring machines (TBMs) will be required to complete tunneling works along this section of the line, one of which is already busy at work under contract CR202. TBM Jane, launched in May 2025, is a large diameter TBM that will construct the tunnels connecting Turf City station with Bright Hill station on phase 1 of the line. This tunnel will undercross the Central Catchment Nature Reserve (CCNR) without disturbing the surface, a decision that was not undertaken lightly when the line was first planned. Due to concerns from nature groups and other communities, studies were initiated to weigh the benefits of pursuing the direct route over an alternative route avoiding the CCNR entirely. Ultimately, following the studies conducted, the direct route through the CCNR was selected, albeit with some adjustments to the work areas to mitigate impact to the flora and fauna found within the reserve.

In addition to the symbolic start of construction along the second phase, the Minister for Transport - Mr. Jeffrey Siow - also officiated the opening of the phase's Project Information Centre (PIC). Located in Clementi and next to the project site, the PIC serves to allow the community to learn more about the project and its development. On display is a model of the upcoming Clementi station and exhibits of the contracts under this phase of the line. Similar PICs exist in Hougang for Phase 1 of the line and in Punggol for the Punggol extension section.

7 July 2025 - Opening plaque

The PIC will be open to the public from 8 July 2025. Operating hours will be 9.00am to 5.00pm, Monday to Friday. Walk-ins are allowed, but booking an appointment through a link to be released is encouraged.

We look forward to the continued progress along CRL2 with the phase officially underway. May the project be completed safely & in a timely manner.

Sunday, June 8, 2025

CRL - A snapshot in May 2025

An overview of CRL1 contracts CR101 - CR111 as of May 2025.
Top (L - R) : CR101 - Changi East Depot, CR102 - Tunnels, CR103 - Aviation Park station
Middle (L - R) : CR106 - Loyang station, CR107 - Pasir Ris East station, CR108 - Pasir Ris station
Bottom (L - R) : CR109 - Tampines North station, CR110 - Large bored tunnel, CR111 - Defu station

An overview of CRL1 contracts CR112 - CR117, CPE contracts P102 & P103 and CRL2 contract CR202 as of May 2025.
Top (L - R) : CR112 - Hougang station, CR113 - Serangoon North station, CR115 - Tavistock station
Middle (L - R) : CR116 - Ang Mo Kio station, N109A - Teck Ghee station, CR117 - Bright Hill station
Bottom (L - R) : P102 - Elias station, P103 - Cripple siding, CR202 - Large bored tunnel

An overview of CRL2 contracts CR205 - CR211 as of May 2025.
Top (L - R) : CR205 - King Albert Park station, CR206 - Maju station
Middle (L - R) : CR207 - Tunnels, CR208 - Clementi station, CR209 - West Coast station
Bottom (L - R) : CR210 - Tunnels, CR211 - Jurong Lake District station

It has been a while since we've done a snapshot feature of the Cross Island Line (CRL), with our last being done in February for the Punggol Extension. Part of this stems for the works being "less noticeable", since the majority of this takes place underground and relatively out of sight. Another part is that it also appears that updates on the CRL aren't as popular compared to updates on other lines (granted, the above ground line updates are A LOT more interesting as you actually see things change with most monthly updates). Nonetheless, we thought it's time to see where the CRL is in progress with this rather comprehensive mid-year update.

Sunday, April 6, 2025

CR208 - Clementi EWL A&A works for paid transfers

Brochure for contract CR208's Clementi station.

A common hot topic question that has been asked many times has been - will Clementi station feature paid transfers between the East-West Line (EWL) and Cross Island Line (CRL)? The answers are simple and yet complex at the same time. If one were to look at the system map, the interchange symbols at Clementi station indicate an integrated interchange that does not require a tap out transfer, unlike those clearly demarcated at Riviera, Tampines, Newton and Bukit Panjang stations. Now that we've gotten that first clue out of the way, we come to the more complex question - how will the paid transfers be done then?

Thursday, February 6, 2025

CRL2 - A snapshot in January 2025

A view of the various contract sites for Cross Island Line phase 2 in January 2025.
Top: Contract CR207 along Clementi Road
Middle (L - R): CR17 - Clementi station, CR18 - West Coast station
Bottom (L - R): Contract CR210 site near Jurong Town Hall station, CR19 - Jurong Lake District

Our last summary update for phase 2 of the Cross Island Line (CRL) was some time ago. With the recent public holidays in the previous month, we managed to make a few visits to some of the sites along the southern section of this line. Do check out the updates to find out more on the progress of the contracts thus far after the jump!

Friday, September 6, 2024

CRL - A snapshot in August 2024

 

An overview of 2 CRL1 contracts as of August 2024.
Top: Changi East depot
Bottom: Contract CR110 launch shaft at Paya Lebar Air Base

Overview of CRL1 stations CR3 - CR11 as of August 2024.
Top (L - R): CR3 - Loygang, CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris
Middle (L - R): CR6 - Tampines North, CR7 - Defu, CR8 - Hougang
Bottom (L - R): CR9 - Serangoon North, CR10 – Tavistock, CR11 – Ang Mo Kio


Overview of CRL1 stations CR12 – CR13, CPE stations CP2 – CP4 & CRL2 stations CR15 –
CR18 as of August 2024.
Top (L - R): CR12 – Teck Ghee, CR13 – Bright Hill, CP2 – Elias
Middle (L - R): CP3 – Riviera, CP4 – Punggol, CR15 – King Albert Park
Bottom (L - R): CR16 – Maju, CR17 – Clementi, CR18 – West Coast


With the award of contract CR207 for tunnels between Maju and Clementi stations in August, all civil contracts across the Cross Island Line (CRL)'s phases 1, 2 and Punggol extension have been awarded. Work on phase 1 and the Punggol extension were well underway while works along phase 2 were at different stages owing to the contract award progress.

Friday, June 7, 2024

CRL - A snapshot in May 2024

Overview of CRL1 stations CR4 - CR7 as at May 2024.
Top (L - R): CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris
Bottom (L - R): CR6 - Tampines North, CR7 - Defu


Overview of CRL1 stations CR8 - CR11 as at May 2024.
Top (L - R): CR8 - Hougang, CR9 - Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio


Overview of CRL1 stations CR12, CR13, CR15 & CR17 as at May 2024.
Top (L - R): CR12 - Teck Ghee, CR13 - Bright Hill
Bottom (L - R): CR15 - King Albert Park, CR17 - Clementi

Another week, and another month goes by. We're now clearly heading towards the middle of the year with June underway. Here's a look back at the progress made at the various Cross Island Line station sites in May 2024. There's a bit more to see now that some of the Tunnel Boring Machines are in the ground and beginning their boring journeys through the east to construction the line.

Friday, April 5, 2024

CRL - A snapshot in March 2024

Overview of CRL1 stations CR4 - CR13 as at March 2024.
Top (L - R): CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris, CR7 - Defu
Middle (L - R): CR8 - Hougang, CR9 - Serangoon North, CR10 - Tavistock
Bottom (L - R): CR11 – Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill


Overview of CPE & CRL2 stations CP2 - CP4 & CR14 - CR19 as at March 2024.
Top (L - R): CP2 - Elias, CP3 - Riviera, CP4 - Punggol
Middle (L - R): CR14 - Turf City, CR15 - King Albert Park, CR16 - Maju
Bottom (L - R): CR17 - Clementi, CR18 - West Coast, CR19 - Jurong Lake District

It's been a whirlwind first quarter of the year. We take the opportunity to check in on the progress of the various construction sites along the Cross Island Line (CRL)'s various phases in the month of March and provide a glimpse at the progress being made. Do check out the various projects after the jump.

Thursday, March 14, 2024

CR208 - Beginning of works for Clementi

 

24 February 2024 - A view of the existing East-West Line (EWL) Clementi station, Clementi
Avenue 4 & the plot vacated by the demolished apartment blocks and open air carpark.

A render of Clementi Cross Island Line (CRL) station.
Source: Aurecon

The contract to build Clementi interchange along the Cross Island Line (CRL) was awarded to a joint venture between China Communications Construction Company & Sinohydro Corporation in Q4 2023, together with contract CR205 for King Albert Park. The press release for the award of both contracts, the one for Clementi being contract CR208, stated that works for both were due to commence by Q1 2024. True to the press release's word, works for both contracts have begun. More after the jump.

Friday, March 8, 2024

CRL - A snapshot in February 2024

 

Overview of CRL1 stations CR3 - CR13 as at mid-to-late February 2024.
Top (L - R): CR3 - Loyang, CR5/CP1 - Pasir Ris, CR6 - Tampines North
Middle (L - R): CR7 - Defu, CR8 - Hougang, CR9 - Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR13 - Bright Hill


Overview of CPE & CRL2 stations CP02 - CP04 & CR15 - CR18 as of mid-to-late February 2024.
Top (L - R): CP02 - Elias & CP03 - Riviera
Middle (L - R): CP05 - Punggol, CR15 - King Albert Park, CR16 - Maju
Bottom (L - R): CR17 - Clementi & CR18 - West Coast

The first few months of the year have quickly past and we're slowly getting back into the monthly routines. Here's a snapshot update of the Cross Island Line (CRL)'s various stages of construction for the month of February with work started on phase 1 and the Punggol Extension. The latest phase announced - phase 2 - has also begun early works which we also explore in this update.

Saturday, December 30, 2023

CPE & CRL2 - year-end update 2023

 

The 9 station sites of CPE & CRL2 as of end-2023.

2023 was an eventful year for both the Cross Island Line (CRL)'s Punggol Extension (CPE) & Phase 2 (CRL2) sections with the ground breaking ceremony and contracts being awarded respectively. With the ground breaking ceremony taking place this year, work has began at all 3 station sites under the offshoot branch which connects the main CRL line at Pasir Ris with Punggol - a precursor to the long spoken about Northshore Line which would have eventually connected Punggol and Woodlands. Over at CRL2, contract awarded began, with 3 of the 9  civil contracts awarded through the year. All in all, 2023 has been exciting for the phase 2 stations.

Friday, November 10, 2023

CRL1, CPE & CRL2 - A snapshot in October 2023

 

Top (L - R): CR105 - Large diameter tunnel, CR3 - Loyang, CR4 - Pasir Ris East
Middle (L - R): CR5/CP1 - Pasir Ris, CR6 - Tampines North, CR7 - Defu
Bottom (L - R): CR8 - Hougang, CR9 - Serangoon North, CR10 – Tavistock


Top (L - R): CR11 - Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill
Middle (L - R): CP2 - Elias, CP3 - Riviera, CR15 - King Albert Park
Bottom (L - R): CR16 - Maju, CR17 - Clementi, CR18 - West Coast


Here's a look at the progress made at the various Cross Island Line (CRL) sites across Phases 1, 2 & the Punggol Extension in October 2023.

Monday, October 2, 2023

CRL2 - Contract awards for CR205 & CR208

 

A view of the CRL platform at King Albert Park station.
Source: LTA

The second phase of the Cross Island Line (CRL) achieved a milestone today with the award of 2 contracts - CR205 & CR208. The contracts are for the design & construction of King Albert Park and Clementi interchange stations respectively.

Monday, July 24, 2023

CRL2 - Release of contract CR203 for Turf City

 

24 July 2023 - Tender for contract CR203
Source: LTA

Today, the Land Transport Authority (LTA) floated the tender for contract CR203. This contract involves the construction of Turf City station and associated tunnels connecting to King Albert Park station in neighbouring contract CR205. Contract CR203 is the sixth contract floated for tender under the Cross Island Line's (CRL) phase 2 which continues the line from Bright Hill to Jurong Lake District. CRL2 is due to commence operations in 2032.

To date, of the contracts floated for tenders, 1 has been awarded, 3 have been closed for evaluation of tender bids & 2 remain open. We've done up a table for ease of reference.

Contract Number

Status

Bidders

CR202

Awarded

Obayashi – STEC JV (Successful)

CR203
(Turf City)

Open

Pending – closing 22 Dec 2023

CR205
(King Albert Park)

Closed for evaluation

1. China Communications Construction Co. Ltd

2. Gammon Construction & Engineering Pte Ltd

3. Lum Chang Building Contractors Pte Ltd

4. Ssangyong Engineering & Construction Co. Ltd

CR206
(Maju)

Open

Pending – closing 31 July 2023

CR208
(Clementi)

Closed for evaluation

1. CES_SDC Pte Ltd

2. China Communications Construction Co. Ltd

3. Daelim Engineering & Construction Co Ltd.

4. Sato Kogyo (S) Pte Ltd

CR209
(West Coast)

Closed for evaluation

1. CES_SDC Pte Ltd

2. China Jingye Engineering Corporation Ltd

3. China Railway First Group Co. Ltd

4. Gamuda Berhad

5. Shanghai Tunnel Engineering Co Pte Ltd (STEC)

With the latest tender floated, the contracts for 5 of the 6 stations along CRL2 have been successfully tendered. The remaining contract for Jurong Lake District station has yet to be floated, along with 2 other contracts - likely to be contracts for tunneling works. The remaining contracts are numbered CR207, CR210 & CR211.

This post is also available on Instagram & Facebook.

Sunday, May 21, 2023

CR2016 - Advanced works for CRL2

 

21 May 2023 - The beginning of hoarding along Clementi Road.

21 May 2023 - Hoarding along Clementi Road.

Recently if you've travelled along Clementi Road, especially around the Singapore Institute of Management (SIM) / Singapore University of Social Sciences (SUSS) stretch, you may have noticed green hoarding along the boundary of the road. Ever wondered what the hoarding is for? Could it be that works for the Cross Island Line (CRL) phase 2 are already beginning? Find out more after the jump.

Saturday, February 11, 2023

Clementi pre-construction 2022

2 October 2022 - An aerial view of Clementi Avenue 5, where one of the
station exits will be located near the neighbourhood police post.

Clementi town is currently served by an existing station on the East-West Line and was one of the first towns to be served by the MRT network when it was first built in the 1980's. The town will be served by another line some 4 to 5 decades following the implementation of the original compass line system. As the environment impact studies were only conducted for areas of concern at Clementi Forest (Maju station), Holland Plains (King Albert Park station) & the central catchment nature reserve (Turf City & large diameter bored tunnel to Bright Hill), there are no available maps to show the layout of stations further west. Nonetheless, we have a collection of images taken over the course of 2022 before construction begins.

Friday, January 6, 2023

CR205 & CR208 - 2nd pre-qualifications

 

3 January 2023 - Companies that have successfully pre-qualified after the

second round for contract CR205.


3 January 2023 - Companies that have successfully pre-qualified after
the second round for contract CR208.

Last year, 3 contracts were tendered for the Cross Island Line (CRL) phase 2 for the construction of King Albert Park interchange (contract CR205), Clementi interchange (contract CR208) & West Coast station (contract CR209). Concurrently, the Land Transport Authority (LTA) also launched a second round of pre-qualification for the contracts, for which has since been closed for the former but is still open till 16 January 2023 for the latter.

As the pre-qualification exercise for both contracts CR205 & CR208 have concluded, the list of eligible companies for bidding for the projects has been published on government portal Gebiz. There are 2 companies that can proceed to submit tender bids for contract CR205 and 6 that can submit bids for contract CR208. It will be interesting to see which companies make a final bid for the respective contracts.

We will keep a keen watch on the contract bidding process and provide updates once available.

This post is also available on Instagram.