Showing posts with label CR206. Show all posts
Showing posts with label CR206. Show all posts

Saturday, August 8, 2026

CRL - A snapshot in July 2026

A compilation of the various sites across Phases 1 and 2 in July 2026.

With the announcement of the Cross Island Line (CRL)'s final phase on 31 July 2026, we now know that the line will stretch for 67km, making this line the longest in the country - beating out the East-West Line (EWL)'s record of 54km by a fair bit. This means that the CRL is a really big project, spanning end-to-end across the entire country. While the EWL also crosses the island from east to west, it mostly sticks to the southern section of the island. In comparison, the CRL swings further north and south than the EWL, making its route much more varied and spread out. This translates into it being much more difficult to easily visit and keep track of all contract sites.

For this update, we tried to cover as much ground as we could to give you an idea of where the line stands in progress. As phase 3 was only announced right at the end of the month, we won't be yet including that section in this update. Nonetheless, all the previous phases of the line that were officially announced are covered in this update in some way, form or manner. There's a lot to unpack, so jump right on in after the jump.

Thursday, March 26, 2026

CRL2 - A snapshot in March 2026

Overview of CRL2 stations CR19 - CR15 & contract CR210 & CR207 sites as at March 2026.
Top (L - R): CR19 - Jurong Lake District, CR210 launch shaft
Middle (L - R): CR18 - West Coast, CR17 - Clementi, CR207 launch shaft
Bottom (L - R): CR16 - Maju, CR15 - King Albert Park

Phase 2 of the Cross Island Line (CRL) is fast approaching road diversion season. In fact, this section of the line may have already crossed the threshold into the road diversion territory, with the first major diversion having taken place at the Maju station site. Nonetheless, other sites are likewise gearing up for their diversion-eras as well. Which sites are these and which roads will be diverted? Find out all that & more after the jump!

Saturday, November 1, 2025

CRL - A snapshot in October 2025

Overview of CRL1 stations CR4 - CR12 as at October 2025.
Top (L - R): CR4 – Pasir Ris East, CR5/CP1 – Pasir Ris, CR6 – Tampines North
Middle (L - R): CR7 – Defu, CR8 – Hougang, CR9 – Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR12 – Teck Ghee


Overview of CPE stations CP2 - CP4 & CRL2 stations CR16 - CR19 as at October 2025.
Top (L - R): CP2 – Elias, CP3 – Riviera, CP4 – Punggol
Middle (L - R): CR16 – Maju, CR207 – Twin bored tunnels, CR17 – Clementi
Bottom (L - R): CR18 – West Coast, CR210 – Twin bored tunnels, CR19 – Jurong Lake District

It's been a while since we've done such an extensive coverage of the Cross Island Line (CRL) across its three current phases that have been announced thus far, hence we thought we'd let October be our month of diversity. Updates for this month stretch from Pasir Ris East all the way to Punggol & Jurong Lake District. If you've been curious on how things were progressing, this post is for you. Do be ready, this update's kind of MEGA.

Monday, July 7, 2025

CRL2 Groundbreaking ceremony

7 July 2025 - A group photo with contractors of CRL2.

Today, the Land Transport Authority (LTA) held a groundbreaking ceremony to mark the official commencement of construction on phase 2 of the Cross Island Line (CRL). Connecting 6 stations over 15km of track, the section of line will see the expansion of Singapore's rail network reach areas in the west currently not well covered by the system. Notably, the future housing estate on the site of the former turf club will be served by the MRT and residents at West Coast will have a station to call their own. Also standing to benefit, students at the Singapore University of Social Sciences (SUSS) and Singapore Institute of Management (SIM) will be served by the upcoming Maju station. Stations along this section of the line are Turf City, King Albert Park, Maju, Clementi, West Coast and Jurong Lake District. King Albert Park and Clementi stations will connect to the existing Downtown and East-West lines respectively, allowing convenient transfers for commuters.

Early works under the 9 contracts that make up phase 2 have already commenced, thus today's ceremony is more symbolic in nature. Some of the works that have begun include the demolition of existing structures at the project sites, utility diversions and construction of diaphragm walls for sections where excavation works will be required. The 9 contracts consist of 3 contracts for tunneling between stations and 6 contracts for the construction of stations, some which also include the construction of connecting tunnels.

A total of 11 tunnel boring machines (TBMs) will be required to complete tunneling works along this section of the line, one of which is already busy at work under contract CR202. TBM Jane, launched in May 2025, is a large diameter TBM that will construct the tunnels connecting Turf City station with Bright Hill station on phase 1 of the line. This tunnel will undercross the Central Catchment Nature Reserve (CCNR) without disturbing the surface, a decision that was not undertaken lightly when the line was first planned. Due to concerns from nature groups and other communities, studies were initiated to weigh the benefits of pursuing the direct route over an alternative route avoiding the CCNR entirely. Ultimately, following the studies conducted, the direct route through the CCNR was selected, albeit with some adjustments to the work areas to mitigate impact to the flora and fauna found within the reserve.

In addition to the symbolic start of construction along the second phase, the Minister for Transport - Mr. Jeffrey Siow - also officiated the opening of the phase's Project Information Centre (PIC). Located in Clementi and next to the project site, the PIC serves to allow the community to learn more about the project and its development. On display is a model of the upcoming Clementi station and exhibits of the contracts under this phase of the line. Similar PICs exist in Hougang for Phase 1 of the line and in Punggol for the Punggol extension section.

7 July 2025 - Opening plaque

The PIC will be open to the public from 8 July 2025. Operating hours will be 9.00am to 5.00pm, Monday to Friday. Walk-ins are allowed, but booking an appointment through a link to be released is encouraged.

We look forward to the continued progress along CRL2 with the phase officially underway. May the project be completed safely & in a timely manner.

Sunday, June 8, 2025

CRL - A snapshot in May 2025

An overview of CRL1 contracts CR101 - CR111 as of May 2025.
Top (L - R) : CR101 - Changi East Depot, CR102 - Tunnels, CR103 - Aviation Park station
Middle (L - R) : CR106 - Loyang station, CR107 - Pasir Ris East station, CR108 - Pasir Ris station
Bottom (L - R) : CR109 - Tampines North station, CR110 - Large bored tunnel, CR111 - Defu station

An overview of CRL1 contracts CR112 - CR117, CPE contracts P102 & P103 and CRL2 contract CR202 as of May 2025.
Top (L - R) : CR112 - Hougang station, CR113 - Serangoon North station, CR115 - Tavistock station
Middle (L - R) : CR116 - Ang Mo Kio station, N109A - Teck Ghee station, CR117 - Bright Hill station
Bottom (L - R) : P102 - Elias station, P103 - Cripple siding, CR202 - Large bored tunnel

An overview of CRL2 contracts CR205 - CR211 as of May 2025.
Top (L - R) : CR205 - King Albert Park station, CR206 - Maju station
Middle (L - R) : CR207 - Tunnels, CR208 - Clementi station, CR209 - West Coast station
Bottom (L - R) : CR210 - Tunnels, CR211 - Jurong Lake District station

It has been a while since we've done a snapshot feature of the Cross Island Line (CRL), with our last being done in February for the Punggol Extension. Part of this stems for the works being "less noticeable", since the majority of this takes place underground and relatively out of sight. Another part is that it also appears that updates on the CRL aren't as popular compared to updates on other lines (granted, the above ground line updates are A LOT more interesting as you actually see things change with most monthly updates). Nonetheless, we thought it's time to see where the CRL is in progress with this rather comprehensive mid-year update.

Friday, September 6, 2024

CRL - A snapshot in August 2024

 

An overview of 2 CRL1 contracts as of August 2024.
Top: Changi East depot
Bottom: Contract CR110 launch shaft at Paya Lebar Air Base

Overview of CRL1 stations CR3 - CR11 as of August 2024.
Top (L - R): CR3 - Loygang, CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris
Middle (L - R): CR6 - Tampines North, CR7 - Defu, CR8 - Hougang
Bottom (L - R): CR9 - Serangoon North, CR10 – Tavistock, CR11 – Ang Mo Kio


Overview of CRL1 stations CR12 – CR13, CPE stations CP2 – CP4 & CRL2 stations CR15 –
CR18 as of August 2024.
Top (L - R): CR12 – Teck Ghee, CR13 – Bright Hill, CP2 – Elias
Middle (L - R): CP3 – Riviera, CP4 – Punggol, CR15 – King Albert Park
Bottom (L - R): CR16 – Maju, CR17 – Clementi, CR18 – West Coast


With the award of contract CR207 for tunnels between Maju and Clementi stations in August, all civil contracts across the Cross Island Line (CRL)'s phases 1, 2 and Punggol extension have been awarded. Work on phase 1 and the Punggol extension were well underway while works along phase 2 were at different stages owing to the contract award progress.

Wednesday, July 24, 2024

CR206 - Preparation works for Maju's construction

 

23 June 2024 - An aerial view to the north of the Maju station site.

23 June 2024 - An aerial view to the south of the Maju station site.

Contract CR206 was the fifth civil contract awarded for the Cross Island Line (CRL)'s phase 2 following the contracts for the large diameter single bored tunnel through the nature reserve, King Albert Park, Clementi & West Coast stations. The award of the contract was announced in end-January this year, with works expected to commence in Q2 of the year. The site has been used thus far for contract CR2016, which is an advanced works contract to relocate utility lines and pipes. The remainder of these works still appear to be going on at the main site of the station's location.

Friday, April 5, 2024

CRL - A snapshot in March 2024

Overview of CRL1 stations CR4 - CR13 as at March 2024.
Top (L - R): CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris, CR7 - Defu
Middle (L - R): CR8 - Hougang, CR9 - Serangoon North, CR10 - Tavistock
Bottom (L - R): CR11 – Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill


Overview of CPE & CRL2 stations CP2 - CP4 & CR14 - CR19 as at March 2024.
Top (L - R): CP2 - Elias, CP3 - Riviera, CP4 - Punggol
Middle (L - R): CR14 - Turf City, CR15 - King Albert Park, CR16 - Maju
Bottom (L - R): CR17 - Clementi, CR18 - West Coast, CR19 - Jurong Lake District

It's been a whirlwind first quarter of the year. We take the opportunity to check in on the progress of the various construction sites along the Cross Island Line (CRL)'s various phases in the month of March and provide a glimpse at the progress being made. Do check out the various projects after the jump.

Friday, March 8, 2024

CRL - A snapshot in February 2024

 

Overview of CRL1 stations CR3 - CR13 as at mid-to-late February 2024.
Top (L - R): CR3 - Loyang, CR5/CP1 - Pasir Ris, CR6 - Tampines North
Middle (L - R): CR7 - Defu, CR8 - Hougang, CR9 - Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR13 - Bright Hill


Overview of CPE & CRL2 stations CP02 - CP04 & CR15 - CR18 as of mid-to-late February 2024.
Top (L - R): CP02 - Elias & CP03 - Riviera
Middle (L - R): CP05 - Punggol, CR15 - King Albert Park, CR16 - Maju
Bottom (L - R): CR17 - Clementi & CR18 - West Coast

The first few months of the year have quickly past and we're slowly getting back into the monthly routines. Here's a snapshot update of the Cross Island Line (CRL)'s various stages of construction for the month of February with work started on phase 1 and the Punggol Extension. The latest phase announced - phase 2 - has also begun early works which we also explore in this update.

Wednesday, January 31, 2024

CR206 - Contract for Maju station awarded

 

A render of the Maju station platform.
Source: LTA

This morning, the Land Transport Authority (LTA) announced the award of another Cross Island Line (CRL) Phase 2 civil contract to a successful tenderer. The contract, CR206, is for the construction of Maju station and tunnels connecting to King Albert Park station, which will be built under contract CR205. With the award of contract CR206 contractor KTC Civil Engineering & Construction Pte Ltd, a total of 5 civil contracts for CRL2 have since been awarded successfully.

Saturday, December 30, 2023

CPE & CRL2 - year-end update 2023

 

The 9 station sites of CPE & CRL2 as of end-2023.

2023 was an eventful year for both the Cross Island Line (CRL)'s Punggol Extension (CPE) & Phase 2 (CRL2) sections with the ground breaking ceremony and contracts being awarded respectively. With the ground breaking ceremony taking place this year, work has began at all 3 station sites under the offshoot branch which connects the main CRL line at Pasir Ris with Punggol - a precursor to the long spoken about Northshore Line which would have eventually connected Punggol and Woodlands. Over at CRL2, contract awarded began, with 3 of the 9  civil contracts awarded through the year. All in all, 2023 has been exciting for the phase 2 stations.

Friday, November 10, 2023

CRL1, CPE & CRL2 - A snapshot in October 2023

 

Top (L - R): CR105 - Large diameter tunnel, CR3 - Loyang, CR4 - Pasir Ris East
Middle (L - R): CR5/CP1 - Pasir Ris, CR6 - Tampines North, CR7 - Defu
Bottom (L - R): CR8 - Hougang, CR9 - Serangoon North, CR10 – Tavistock


Top (L - R): CR11 - Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill
Middle (L - R): CP2 - Elias, CP3 - Riviera, CR15 - King Albert Park
Bottom (L - R): CR16 - Maju, CR17 - Clementi, CR18 - West Coast


Here's a look at the progress made at the various Cross Island Line (CRL) sites across Phases 1, 2 & the Punggol Extension in October 2023.

Monday, July 24, 2023

CRL2 - Release of contract CR203 for Turf City

 

24 July 2023 - Tender for contract CR203
Source: LTA

Today, the Land Transport Authority (LTA) floated the tender for contract CR203. This contract involves the construction of Turf City station and associated tunnels connecting to King Albert Park station in neighbouring contract CR205. Contract CR203 is the sixth contract floated for tender under the Cross Island Line's (CRL) phase 2 which continues the line from Bright Hill to Jurong Lake District. CRL2 is due to commence operations in 2032.

To date, of the contracts floated for tenders, 1 has been awarded, 3 have been closed for evaluation of tender bids & 2 remain open. We've done up a table for ease of reference.

Contract Number

Status

Bidders

CR202

Awarded

Obayashi – STEC JV (Successful)

CR203
(Turf City)

Open

Pending – closing 22 Dec 2023

CR205
(King Albert Park)

Closed for evaluation

1. China Communications Construction Co. Ltd

2. Gammon Construction & Engineering Pte Ltd

3. Lum Chang Building Contractors Pte Ltd

4. Ssangyong Engineering & Construction Co. Ltd

CR206
(Maju)

Open

Pending – closing 31 July 2023

CR208
(Clementi)

Closed for evaluation

1. CES_SDC Pte Ltd

2. China Communications Construction Co. Ltd

3. Daelim Engineering & Construction Co Ltd.

4. Sato Kogyo (S) Pte Ltd

CR209
(West Coast)

Closed for evaluation

1. CES_SDC Pte Ltd

2. China Jingye Engineering Corporation Ltd

3. China Railway First Group Co. Ltd

4. Gamuda Berhad

5. Shanghai Tunnel Engineering Co Pte Ltd (STEC)

With the latest tender floated, the contracts for 5 of the 6 stations along CRL2 have been successfully tendered. The remaining contract for Jurong Lake District station has yet to be floated, along with 2 other contracts - likely to be contracts for tunneling works. The remaining contracts are numbered CR207, CR210 & CR211.

This post is also available on Instagram & Facebook.

Sunday, May 21, 2023

CR2016 - Advanced works for CRL2

 

21 May 2023 - The beginning of hoarding along Clementi Road.

21 May 2023 - Hoarding along Clementi Road.

Recently if you've travelled along Clementi Road, especially around the Singapore Institute of Management (SIM) / Singapore University of Social Sciences (SUSS) stretch, you may have noticed green hoarding along the boundary of the road. Ever wondered what the hoarding is for? Could it be that works for the Cross Island Line (CRL) phase 2 are already beginning? Find out more after the jump.

Friday, January 20, 2023

Maju pre-construction 2022

 

31 December 2022 - A view from the pedestrian overhead bridge at Ngee Ann Polytechnic,
looking at the Clementi Forest, a small portion of which will be used for the Maju station.

Maju station will be located along Clementi Road, near the Singapore University of Social Sciences (SUSS) & Singapore Institute of Management (SIM) HQ. Originally planned to be located along the road side table and within the Clementi Forest, subsequent environmental surveys and local's awareness of the existence of the natural landscape lead to the adoption of an alternative station site and work areas located underneath Clementi Road itself.

Saturday, November 5, 2022

CRL2 - Through the Central Catchment Nature Reserve

 


The Straits Times recently published a short video explaining the behind the scenes work by the Land Transport Authority (LTA) in the engineering planning works behind the section of the Cross Island Line (CRL) alignment interacting with nature aspects. Work sites were moved several times and other measures were taken by LTA to ensure as minimal impact as possible is done to the surrounding reserves and habitats. Not covered in the video, is also the shifting of Maju station away from the forested areas to preserve the natural environment and reduce the impact of construction.

More information can be obtained on LTA's website. Link to youtube video.

Thursday, October 13, 2022

CRL2 - Some renders & EIS reports

 

A render of an exit of Turf City station.
Source: LTA

The Land Transport Authority (LTA) has recently published the Environmental Impact Study (EIS) reports on their website. Within the reports were a few renders of Turf City and King Albert Park stations. Other details were also unveiled within the reports, such as the stations at Maju & Turf City potentially having cripple sidings integrated into the stations and a future knock out panel being provisioned for a "paid link" at Maju station. A heritage study report by the Urban Redevelopment Authority did not yield any other results.

Tuesday, September 20, 2022

CRL2 Announced

 

20 September 2022 - Photo taking at the ministerial visit to the East Coast depot.

CHANGI SOUTH, SINGAPORE - On 20th September, the Land Transport Authority (LTA) unveiled the second phase of the hotly anticipated Cross Island Line (CRL). CRL2 will span 15km, connecting to the first phase at Bright Hill and ending at the Jurong Lake District. Along the way, the line crosses with the Downtown Line (DTL) & East-West Line (EWL), offering commuters an alternative route between the east and west.

Tuesday, September 6, 2022

CRL2 - What's next?

Overview of the stages in the development of a Rapid Transit System.

With works on phase 1 of the Cross Island Line (CRL) mostly under way, the next hotly anticipated development for the line will be the announcement of station locations along the phase 2 section. Join us as we explore some of the key milestones to hit before construction works can commence.

Friday, August 5, 2022

CRL2 - Speculated Station Locations

A map of the expected phase 2 of the Cross Island Line. Own production.

As it has been more than 2 years since Cross Island Line (CRL) Punggol Extension was announced, we are expecting news of the next phase of the line to be announced this year. With an expected completion date of 2032, we foresee tenders for advanced contracts to be published soon. Earlier in June, pre-qualifications for 8 contracts for the second phase of the line were called for.

The Urban Redevelopment Authority (URA) Long-Term Plan.
Source: URA

The Urban Redevelopment Authority (URA) also published the latest Long-Term Plan in June 2022 which showed the notional full alignment of the CRL. By overlaying the long-term plan map over a geographic map, we were able to collaborate the supporting data and information with the latest sightings of soil investigation works to compile a list of probable station locations for the CRL2 section. This section of the CRL will continue from the tunnel section directly crossing below the Central Catchment Nature Reserve (CCNR), and ends at Jurong Lake District.

We expect that there will be a total of 6 stations in this section, which stretches over 15km consisting of 5km below the CCNR, and 10km of tunnels between the 6 stations.
Geographical map of our expected CRL2 stations & alignment based on URA's long term plan.