Sunday, July 26, 2026

CRL1, CPE & CRL2 - Tunneling update for June

January 2026 - Factory Acceptance Test for contract CR203 tunnel boring machines in China.
Source: LinkedIn

June was quite a significant month for the Cross Island Line (CRL)'s tunneling works. Significant progress has been made along Phase 1 and along the Punggol Extension. We take a look at the some of the contracts where tunneling works made progress in the month of June.

Thursday, April 30, 2026

CPE - A snapshot in April 2026

Overview of CPE stations as at April 2026.
Top: CP2 - Elias
Middle: CP3 - Riviera
Bottom: CP4 - Punggol

We're beginning the April snapshots with a recap of the Cross Island Line's Punggol Extension (CPE) where things are beginning to ramp up as tunneling works for the entire length of the phase commence. Station works have also progressed at the three station sites under this phase of the line. Find out more as we cover the brief summary of progress made at each station site.

Saturday, August 9, 2025

CRL - A snapshot in July 2025

Overview of CRL1 works under contracts CR106 - CR117 as at July 2025.
Top (L - R): CR106 - Loyang, CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris, CR6 - Tampines North
Middle (L - R): CR110 – Large diameter tunnel, CR7 - Defu, CR8 - Hougang, CR9 - Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill

There's a fair bit to update in this snapshot of the Cross Island Line (CRL) for July 2025. This update will mainly focus on progress along phase 1 of the line, the section with the most progress thus far due to the section's earlier announcement, contract award and commencement in general. Nonetheless, tunneling is also underway across all announced phases thus far, so we will touch a little on the progress made on that front thus far. All this & more after the jump.

Sunday, June 8, 2025

CRL - A snapshot in May 2025

An overview of CRL1 contracts CR101 - CR111 as of May 2025.
Top (L - R) : CR101 - Changi East Depot, CR102 - Tunnels, CR103 - Aviation Park station
Middle (L - R) : CR106 - Loyang station, CR107 - Pasir Ris East station, CR108 - Pasir Ris station
Bottom (L - R) : CR109 - Tampines North station, CR110 - Large bored tunnel, CR111 - Defu station

An overview of CRL1 contracts CR112 - CR117, CPE contracts P102 & P103 and CRL2 contract CR202 as of May 2025.
Top (L - R) : CR112 - Hougang station, CR113 - Serangoon North station, CR115 - Tavistock station
Middle (L - R) : CR116 - Ang Mo Kio station, N109A - Teck Ghee station, CR117 - Bright Hill station
Bottom (L - R) : P102 - Elias station, P103 - Cripple siding, CR202 - Large bored tunnel

An overview of CRL2 contracts CR205 - CR211 as of May 2025.
Top (L - R) : CR205 - King Albert Park station, CR206 - Maju station
Middle (L - R) : CR207 - Tunnels, CR208 - Clementi station, CR209 - West Coast station
Bottom (L - R) : CR210 - Tunnels, CR211 - Jurong Lake District station

It has been a while since we've done a snapshot feature of the Cross Island Line (CRL), with our last being done in February for the Punggol Extension. Part of this stems for the works being "less noticeable", since the majority of this takes place underground and relatively out of sight. Another part is that it also appears that updates on the CRL aren't as popular compared to updates on other lines (granted, the above ground line updates are A LOT more interesting as you actually see things change with most monthly updates). Nonetheless, we thought it's time to see where the CRL is in progress with this rather comprehensive mid-year update.

Friday, September 6, 2024

CRL - A snapshot in August 2024

 

An overview of 2 CRL1 contracts as of August 2024.
Top: Changi East depot
Bottom: Contract CR110 launch shaft at Paya Lebar Air Base

Overview of CRL1 stations CR3 - CR11 as of August 2024.
Top (L - R): CR3 - Loygang, CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris
Middle (L - R): CR6 - Tampines North, CR7 - Defu, CR8 - Hougang
Bottom (L - R): CR9 - Serangoon North, CR10 – Tavistock, CR11 – Ang Mo Kio


Overview of CRL1 stations CR12 – CR13, CPE stations CP2 – CP4 & CRL2 stations CR15 –
CR18 as of August 2024.
Top (L - R): CR12 – Teck Ghee, CR13 – Bright Hill, CP2 – Elias
Middle (L - R): CP3 – Riviera, CP4 – Punggol, CR15 – King Albert Park
Bottom (L - R): CR16 – Maju, CR17 – Clementi, CR18 – West Coast


With the award of contract CR207 for tunnels between Maju and Clementi stations in August, all civil contracts across the Cross Island Line (CRL)'s phases 1, 2 and Punggol extension have been awarded. Work on phase 1 and the Punggol extension were well underway while works along phase 2 were at different stages owing to the contract award progress.

Sunday, April 21, 2024

CPE Project Information Centre - now open!

 

15 February 2024 - A view of the entrance to the CPE PIC prior to the centre's opening.

Earlier this month, the Cross Island Line (CRL) Punggol Extension's (CPE) Project Information Centre (PIC) was officially opened to the public. The PIC is open to the public during weekdays during office hours and is closed on weekends and public holidays. Walk-ins are permitted and no appointment is needed to visit the centre.

Saturday, December 30, 2023

CPE & CRL2 - year-end update 2023

 

The 9 station sites of CPE & CRL2 as of end-2023.

2023 was an eventful year for both the Cross Island Line (CRL)'s Punggol Extension (CPE) & Phase 2 (CRL2) sections with the ground breaking ceremony and contracts being awarded respectively. With the ground breaking ceremony taking place this year, work has began at all 3 station sites under the offshoot branch which connects the main CRL line at Pasir Ris with Punggol - a precursor to the long spoken about Northshore Line which would have eventually connected Punggol and Woodlands. Over at CRL2, contract awarded began, with 3 of the 9  civil contracts awarded through the year. All in all, 2023 has been exciting for the phase 2 stations.

Friday, November 10, 2023

CRL1, CPE & CRL2 - A snapshot in October 2023

 

Top (L - R): CR105 - Large diameter tunnel, CR3 - Loyang, CR4 - Pasir Ris East
Middle (L - R): CR5/CP1 - Pasir Ris, CR6 - Tampines North, CR7 - Defu
Bottom (L - R): CR8 - Hougang, CR9 - Serangoon North, CR10 – Tavistock


Top (L - R): CR11 - Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill
Middle (L - R): CP2 - Elias, CP3 - Riviera, CR15 - King Albert Park
Bottom (L - R): CR16 - Maju, CR17 - Clementi, CR18 - West Coast


Here's a look at the progress made at the various Cross Island Line (CRL) sites across Phases 1, 2 & the Punggol Extension in October 2023.

Tuesday, October 10, 2023

CPE - Groundbreaking ceremony

 

This morning, the Land Transport Authority (LTA) held a groundbreaking ceremony for the Cross Island Line (CRL) - Punggol Extension (CPE) section. Spanning 7.3km and adding 3 additional stations to the line, the ceremony was officiated by Acting Minister for Transport, Mr. Chee Hong Tat. Also in attendance were grassroots leaders for the various districts in which works will take place - Mr. Teo Chee Hean (Pasir Ris Elias), Ms. Yeo Wan Ling (Punggol East) & Mr. Janil Puthucheary (Punggol Central).

Monday, September 18, 2023

P103 - New video for Riviera

 

Source: LTA

Today, the Land Transport Authority (LTA) released a new video showing a flythrough of Riviera station. Featuring 4 exits, Riviera station will allow tap out-transfers between the Punggol LRT East Loop and the Cross Island Line (CRL) Punggol Extension (CPE). It is interesting to note that the station will feature an upper concourse (B1), lower concourse (B2) and platform (B3) all within the paid area. The station will also feature side platforms as a result of the utilisation of a single large bored tunnel for the line from Elias to Punggol stations.

This post is only available on the CRL Construction Blog & will not be cross-posted to Instagram.

Thursday, July 27, 2023

P102 - Analysis of Elias station's location & tunnel alignment

 

Requirements for Wafer Fab industries restrict the line from travelling too close.

We've received some questions on why Elias station must be located at the angle & location that was ultimately chosen. As such, we have done up some visuals and an analysis to help you better understand the factors that play a part in choosing a location for the station.

Sunday, July 23, 2023

P102 - Elias MRT town hall

 


Yesterday, the Land Transport Authority (LTA), together with grassroots leaders and joint venture partner CES_SDC & Chip Eng Seng Contractors held a town hall meeting for residents at Elias Community Club to brief residents about the Elias MRT project. The guest of honour for the town hall event was MP for Pasir Ris West, Mr. Teo Chee Hean.

MP Teo Chee Hean delivering his opening address to residents.


Sunday, July 16, 2023

CRL1 & CPE - Official Telegram Channels

 


Telegram groups have become the new means through which the Land Transport Authority (LTA) has digitised its outreach to stakeholders with new rail projects. The messaging platform has been used as a uni-directional channel through which circulars and updates on the various construction contracts are pushed out to residents, businesses and commuters in the area where construction works are taking place. The first wide-spread adoption was undertaken by the Circle Line Stage 6 (CCL6) project and subsequently adopted by the Jurong Region Line (JRL) as well. It appears that the Cross Island Line (CRL) is using this as well. We attempt to consolidate the links for you to join the Telegram channels as well, which have been rolled out for CRL1 and CPE sections, for which all civil contracts have been awarded thus far. It is assumed that the same will follow for CRL2 once the contracts have been awarded and for CRL3 in due time as well.

Monday, January 2, 2023

P102 - Elias pre-construction

 

27 December 2022

Elias station is the sole remaining station along the Cross Island Line Punggol Extension (CPE) whose contract that has yet to be awarded. We should be able to look forward to the tender award some time this year with construction set to begin within the year as well. The station will be sited on a greenfield site bordered by Pasir Ris Drives 3 & 10 and will feature a station box with a launch and retrieval shaft on either end of the station.

Thursday, May 13, 2021

CPE - Pre-qualification begins

Renders of the CPE stations
Source: Zaobao SG

Recently the Land Transport Authority (LTA) launched pre-qualifications for the Cross Island Line Punggol Extension (CPE) - a 7.3km extension from Pasir Ris to Punggol. The extension will add 3 additional stations to the line with all 3 new stations seemingly featuring side platform configurations There will also be 3 civil contracts for the extension as well - P102, P103 & P105. 

Thursday, April 12, 2018

Soil Investigation: Pasir Ris

A map showing the corridor of the Cross Island Line (CRL).
Source: LTA
Besides serving Punggol, the Cross Island Line (CRL) will also serve Pasir Ris. It is envisaged that Pasir Ris would see up to 3 new MRT stations serving the various neighbourhoods with new rail links. In December 2016 we noted several boreholes around Pasir Ris which are potentially related to the CRL pre-construction works. For the purpose of identifying the districts within Pasir Ris, we will refer to the sections as Elias, Pasir Ris Central and Pasir Ris East.