Today, the Land Transport Authority (LTA) announced that the first Cross Island Line (CRL) trainset under contract CR151 had reached Singapore's shores. Upon arrival, the train will be transported to the Singapore Rail Test Centre (SRTC) in Tuas for testing & integration works. Similar tests were conducted there for the Circle Line (CCL)'s new batch of third generation trains under contract 851E. Did you manage to catch some of the details from the video that LTA put up? Here's what SGMC has uncovered after a closer look (after the jump).
Cross Island Line Construction
Sunday, May 31, 2026
CR151 - The first train arrives
Friday, May 8, 2026
CRL1 - A snapshot in April 2026
Last week, we took a look at the progress of the Cross Island Line (CRL)'s Punggol Extension. This week, we catch up on progress along CRL's phase 1 section, covering 6 contracts under the phase. Join us as we take a look at progress made from Pasir Ris East to Ang Mo Kio in this snapshot update of CRL1.
Thursday, April 30, 2026
CPE - A snapshot in April 2026
![]() |
Overview of CPE stations as at April 2026. |
We're beginning the April snapshots with a recap of the Cross Island Line's Punggol Extension (CPE) where things are beginning to ramp up as tunneling works for the entire length of the phase commence. Station works have also progressed at the three station sites under this phase of the line. Find out more as we cover the brief summary of progress made at each station site.
Thursday, March 26, 2026
CRL2 - A snapshot in March 2026
Phase 2 of the Cross Island Line (CRL) is fast approaching road diversion season. In fact, this section of the line may have already crossed the threshold into the road diversion territory, with the first major diversion having taken place at the Maju station site. Nonetheless, other sites are likewise gearing up for their diversion-eras as well. Which sites are these and which roads will be diverted? Find out all that & more after the jump!
Tuesday, March 24, 2026
CR106 - Completion of WB tunnel
We have just learnt that tunneling works for contract CR106, responsible for the construction of Loyang station and connecting tunnels to Pasir Ris East station, have been completed. The westbound (WB) tunnel boring machine (TBM) successfully docked with the Loyang station box earlier this month. This follows the earlier docking of the eastbound (EB) TBM in January this year. With the latest completion, approximately 16 of the 29 tunnel drives for phase 1 have now been completed.
Sunday, March 8, 2026
CRL - A snapshot in February 2026
It's been a while since we've had a Snapshot update for the Cross Island Line (CRL). Here's one from February 2026, covering several of the sites across Phase 1 and Punggol station along the Punggol Extension. How have works progressed, especially at the line's eastern end? We find out all that and more in this update after the jump.
Thursday, February 19, 2026
CR117 - Completion of westbound tunnel
![]() |
| Graphical representation of tunneling progress for contract CR117. Based on compilation of available information and may not be the most accurate nor up to date. |
Contract CR117 has been one of the more elusive contracts to track progress of, mainly due to the different geology at the location which necessitated different construction methods. For instance, the earth retaining & stabilising structure (ERSS) employed at the site uses bore piles instead of diaphragm walls. Similarly, it has been a little difficult to track the progress of tunneling works. Nonetheless, we've managed to probe a bit more and finally have some idea of the progress when it comes to tunneling.
![]() |
| Undated image - A photo of the slurry tunnel boring machine used for the contract. Source: Skymard / Hnjtx / China Construction Machinery Association |






