Monday, March 27, 2023

CR105 - TBM Factory Acceptance Test

 

February 2023
Source: CREG

Recently the tunnel boring machine (TBM) for contract CR105 underwent its factory acceptance test (FAT). The FAT is where the client, in this case Taisei Corporation - China State Construction Engineering Corporation Joint Venture, goes to the manufacturing factory to see that the machine meets their expectations after production has completed. A series of tests are conducted to ensure that all is in order before the machine is disassembled for delivery to the client's project site.

Friday, March 24, 2023

CR112 - Hougang Q1 2023 update

 

19 March 2023 - A view southwards from across Hougang Avenue 10.

It's been a while since we've had an update on the Cross Island Line (CRL), so we're at Hougang this week to kick things off. Work at the northern half (the closed section of Hougang Central Minor) is more advanced than that at the southern half (near existing Exit A, next to the bus interchange) of the site.

Friday, March 17, 2023

CRL1 Video directory

 


Yesterday, the Land Transport Authority (LTA) released a video showing a flythrough of the upcoming Tampines North station along the Cross Island Line (CRL) phase 1. LTA has been noticeably more active in uploading videos of & marketing the CRL across its social media channels. In addition to the new video on Tampines North, they also uploaded another video on the Rectangular Tunnel Boring Machine (RTBM) being used at the Teck Ghee station under contract N109A to construct subways to two exits located within Bishan-Ang Mo Kio park.