Saturday, December 30, 2023

CPE & CRL2 - year-end update 2023

 

The 9 station sites of CPE & CRL2 as of end-2023.

2023 was an eventful year for both the Cross Island Line (CRL)'s Punggol Extension (CPE) & Phase 2 (CRL2) sections with the ground breaking ceremony and contracts being awarded respectively. With the ground breaking ceremony taking place this year, work has began at all 3 station sites under the offshoot branch which connects the main CRL line at Pasir Ris with Punggol - a precursor to the long spoken about Northshore Line which would have eventually connected Punggol and Woodlands. Over at CRL2, contract awarded began, with 3 of the 9  civil contracts awarded through the year. All in all, 2023 has been exciting for the phase 2 stations.

Wednesday, December 27, 2023

CRL1 year-end update 2023

 

10 stations of the Cross Island Line's phase 1 as at end-2023.
Aviation Park & Defu are not represented in this post.

Sorry this post was a little delayed - got caught up between travelling & work. But we're here and made it to 27th December after all. For this post, we're covering the 10 stations that we have the most pictures of along the Cross Island Line (CRL)'s phase 1. The 2 stations not covered in the post today are Aviation Park and Defu. We may cover them at a later time. Nonetheless, it has been an eventful year for the CRL with the groundbreaking ceremony being held in January 2023. Construction has been well under way at all sites with work in full swing for the construction of the earth retaining & stabilising structures (ERSS). Several intermediate launch shafts have been built as well and excavation commenced at a few sites in particular.

Please be fair warned that this post is a mega-post and extremely photo-heavy. It may suck up a lot of your bandwith after the jump.

Wednesday, December 6, 2023

CRL2 - Contract award for CR209

 

A render of one of the station exits - likely Exit 2.
Source: LTA

A render of the station's interior.
Source: LTA

Today, the Land Transport Authority (LTA) announced the award of contract CR209 for the construction of West Coast station & associated tunnels under the Cross Island Line phase 2. Contract CR209 is the fourth contract under phase 2 to be awarded - the other contract being contract CR202 for the large diameter tunnel through the Central Catchment Nature Reserve and contracts CR205 and CR208 for the construction of King Albert Park and Clementi interchange stations only respectively.