17 September 2023 - An aerial view of the station work site from the eastern end. |
So we're commencing our Q3 updates slightly early with Pasir Ris East up first. Over at the eastern end of the station, works are focused on constructing the diaphragm walls for the launch shaft where tunnel boring machines (TBMs) will be lowered by neighbouring contractor Woh Hup for contract CR106. The TBMs will bore the twin tunnels eastwards, to Loyang station. As such, the launch shaft will be completed under CR107 but subsequently handed over for tunneling works. Upon the completion of tunneling works and first stage concreting, the shaft may be handed back to CR107's contractor, Singapore Engineering & Construction - Sinohydro Corporation Limited joint venture, to complete the remainder of the works.