|
17 September 2023 - An aerial view of the station work site from the eastern end. |
So we're commencing our Q3 updates slightly early with Pasir Ris East up first. Over at the eastern end of the station, works are focused on constructing the diaphragm walls for the launch shaft where tunnel boring machines (TBMs) will be lowered by neighbouring contractor Woh Hup for contract CR106. The TBMs will bore the twin tunnels eastwards, to Loyang station. As such, the launch shaft will be completed under CR107 but subsequently handed over for tunneling works. Upon the completion of tunneling works and first stage concreting, the shaft may be handed back to CR107's contractor, Singapore Engineering & Construction - Sinohydro Corporation Limited joint venture, to complete the remainder of the works.
Information available at the CRL1 PIC
The Cross Island Line (CRL) phase 1 Project Information Centre (PIC) located at Hougang recently opened its doors to the public. The PIC features several touch screen displays which are able to call out information related to the contract as well as show you a flythrough video of how the station will look when completed.
In addition to the details of the contract, architectural models are also available on hand to let you visualise how everything stacks up once completed. The models also allow visitors to have a perspective on how the station integrates with the location, where the exits will be and how the current works facilitate the structure's construction.
For Pasir Ris East, the station will feature a total of 4 exits and 2 ancillary surface structures. The awarded contract - CR107 - was only for the construction of the station building without tunnels. These will be done by neighbouring contracts CR106 to the east & CR108 to the west.
|
31 August 2023 - Project information for contract CR107 available at the PIC. |
|
31 August 2023 - Station map with the 4 entrances marked out. |
|
31 August 2023 - A view of the renders of the 4 station exits. |
|
31 August 2023 - The Pasir Ris East architectural model. |
|
31 August 2023 - A view of Exits 3 & 4 at the model. |
|
31 August 2023 - A cut away cross section showing the longitudinal section of the station. The platform & concourse levels can be seen. |
|
31 August 2023 - A view of Exits 1 & 2 located near the Pasir Ris East Community Club building. |
|
31 August 2023 - A ventilation building will be located opposite Whitesands Primary School. |
Eastern end - the launch shaft
Diaphragm wall works are focused on this end of the station in order to complete the shaft and subsequent excavation before handover to Woh Hup for CR106's tunneling works. Noise barriers have been put up around the neighbouring apartment blocks and Whitesands Primary School to reduce noise generated from the works. In due time, the contractors are likely to engage the students of Whitesands Primary School so that they can understand what the works are for. The students may even take part in a competition to name the TBMs before they commence work.
|
12 August 2023 - A view of the eastern end of the work site. |
|
12 August 2023 - A close up view of the hydrofraise machine on site. |
|
17 September 2023 - Several more machines - hydrofraises & clamshell grabbers - on site. |
|
12 August 2023 - Noise barriers being constructed to contain the noise within the work site as far as possible. |
|
17 September 2023 - Diaphragm wall excavation taking place. |
|
12 August 2023 - An aerial view of the work site. |
|
12 August 2023 |
|
12 August 2023 - Rebar cages being lowered into the diaphragm wall pit that has been excavated. |
|
12 August 2023 |
|
17 September 2023 - An aerial view of the diaphragm walling works. |
|
17 September 2023 |
|
17 September 2023 - A view of the cutters of the hydrofraise machine. |
17 September 2023
The middle - the station box proper
The middle section of the station is where the main box is located. This box will house the exits, concourse and platform levels as well as any ancillary building structures that are required. One such building will be located near block 212A. Work here is not as advanced yet. During a briefing session attended by the team recently, the contractor shared that diaphragm walling works here had not commenced yet. We understand that the focus at the moment is to complete the diaphragm walls of the launch shaft before the remaining sections begin in earnest.
|
12 August 2023 - An aerial view of the site abutting Whitesands Primary School. Rebar cages are on site for use at the launch shaft diaphragm wall excavation site to the left. |
|
12 August 2023 - A close up view of the rebar cages for construction of the diaphragm wall panels. |
|
12 August 2023 - Several machines on site. Noise barriers are being progressively constructed. |
|
12 August 2023 |
|
12 August 2023 - Several betonite silos on site. |
|
17 September 2023 - An auger machine on site. This is used to created bored piles. |
|
17 September 2023 - Rebar cages are visible on site. |
|
17 September 2023 - The contractor shared during the briefing that noise barrier installation has since been completed. |
No comments:
Post a Comment