Tuesday, July 16, 2024

CRL1/CPE/CRL2 - Official Telegram channel listing

 

Unveiled sections of the Cross Island Line as of July 2024.
Source: LTA

With more contracts under the Cross Island Line (CRL)'s phase 2 being awarded, several new Telegram channels have been established to provide residents & stakeholders with updates on construction works. We felt that it was timely to provide a renewed update on the blog as well, for ease of reference should you wish to join the official channels. These groups allow the Land Transport Authority (LTA) and contractors to quickly disseminate information when necessary - for instance, when a road diversion is due to be implemented - allowing stakeholders time to receive the information and understand the changes coming in their vicinity.

CRL Phase

Contract

Telegram group available

CRL 1

CR101

O

CR102

P

CR103

P

CR105

P

CR106

P

CR107

P

CR108

P

CR109

P

CR110

P

CR111

P

CR112

P

CR113

P

CR115

P

CR116

P

N109A

P

CR117

P

CRL Punggol Extension

P102

P

P103

P

P105

P

CRL 2

CR202

P

CR203

O

CR205

P

CR206

P

CR208

P

CR209

P

CR210

O

Phase 1

Contract CR102 - Tunnels between Aviation Park station and Changi East Depot
Unfortunately, the channel is not set up with a QR code that allows easy access. You would need to search for the channel "CR102 Tunnels between Aviation Park Station and Depot" to join. The last post in the channel was made on 14 June 2024. Also unfortunately, this channel is not very active with updates relating to the project itself.

Contract CR103 - Aviation Park station
Unlike the previous contract, this one has a QR code that can be used to easily access the channel. The last update on the channel was dated 03 June 2024. Alas, like the previous contract, this channel is not very active with updates on the project itself.

Contract CR105 - Large diameter single bored tunnel between Aviation Park & Loyang stations
Similar to contract CR103, this contract has a QR code for quick access to the channel. Also similar to contract CR103, the last update on the channel was dated 03 June 2024, with very little activity relating to the project itself.


Contract CR106 - Loyang station & tunnels
This channel has a QR code for quick access. However, it only has 2 posts dated 29 May 2024 and neither of these relate to the contract itself.


Contract CR107 - Pasir Ris East station
The channel for this contract has a QR code for easy access. The last post was made on 28 June 2024. Thankfully, this channel is slightly more active with actual updates that pertain to the contract itself.


Contract CR108 - Pasir Ris station & tunnels
This channel is another one that has a QR code for quick access. The last post within the channel is dated 03 July 2024, and also features updates specific to the contract itself.


Contract CR109 - Tampines North station & tunnels
This contract's channel has a QR code for quick access. The last update was dated 16 July 2024 and consists of a mix of updates from LTA's official Telegram channel and contract-specific circulars.


Contract CR110 - Large diameter single bored tunnel between Paya Lebar Air Base & Defu station
Unfortunately the channel for this contract lacks a QR code for quick access. You would need to search for the channel named "CR110 Design and Construction of Tunnels from Tampines North to Defu". The last post on the channel is dated 15 July 2024 and consists of a mix of updates from the LTA official Telegram channel & contract-specific circulars.

Contract CR111 - Defu station & tunnels
While the official channel does not have a QR code for quick access, the team managed to produce one for your easy access to the channel. The last post within is dated 17 June 2024 and similar to several other channels, features a mix of updates.


Contract CR112 - Hougang station & tunnels
The channel for Hougang station has a QR code for easy access. The latest post within is dated 25 June 2024 and largely consists of contract-specific updates.


Contract CR113 - Serangoon North station
Like the channel for Defu station, contract CR113's channel does not have a QR code for quick access but the team managed to successfully create one for your ease of use. The latest post is dated 16 July 2024 and largely consists of contract-specific updates.


Contract CR115 - Tavistock station & tunnels
Like some other channels, unfortunately Tavistock's lacks a QR code for quick access. To find the channel, you would need to search for "CRL- Tavistock station" to join. The latest post is dated 26 June 2024 and largely consists of contract-specific updates.

Contract CR116 - Ang Mo Kio station & tunnels
Contract CR116 is a rather recent adopter of the Telegram channel communication method, having only publicised the availability towards the end of 2023. A QR code is available for quick access to the channel. The last post is dated 12 July 2024 and largely consists of contract-specific updates.


Contract N109A - Teck Ghee station & North South Expressway tunnels
Contract N109A is also fairly new to the Telegram channel method of communication, with the channel only being created in Q1 2024. A QR code is available to provide quick access. The latest post on the channel is dated 15 July 2024 and consists of a mix of updates that are from LTA's Telegram channel and contract-specific.


Contract CR117 - Bright Hill station & tunnels
A QR code is available for quick access to the last contract from CRL1. The latest post on the channel is dated 14 July 2024 and consists of updates that are contract-specific.


Punggol Extension

Contract P102 - Elias station & tunnels
A QR code is available for users to gain access to the channel. The latest post is dated 16 June 2024. The majority of the posts are contract-specific in nature.


Contract P103 - Riviera station & tunnels
Similar to contract P102, this channel also features a QR code for quick access. The latest post is dated 5 July 2024 and largely consists of updates that are contract-specific in nature.


Contract P105 - Punggol station & cut-and-cover overrun tunnels
Thankfully, a QR code is provided for the channel to allow quick & easy access. The latest post is dated 16 July 2024, with a focus mainly on contract-specific updates.


Phase 2

Contract CR202 - Large diameters single bored tunnel between Sin Ming Walk & Fairways Drive
The channel for contract CR202 was created in Q1 2024 and the latest post is dated 17 June 2024. The updates within consist of a mix with some being forwarded from the LTA Telegram channel while others are more contract-specific in nature.


Contract CR205 - King Albert Park station
This channel was one of the earliest created for contracts under CRL2. A QR code allows users to quickly navigate to the channel. The latest post is dated 10 July 2024, with updates being mostly contract-specific.


Contract CR206 - Maju station & tunnels
As one of the more recently awarded contracts, updates within the channel are a little slower. A QR code is available for quick & easy access to the channel. The latest post is dated 27 June 2024, with the updates featuring a mix between posts from LTA's Telegram channel and contract-specific circulars.


Contract CR208 - Clementi station
The channel for Clementi station is a little more active and dynamic than some others, with the contractor posting several updates on roadshows and stakeholder outreach efforts. A QR code allows users to quickly access the channel. The latest post is dated 12 July 2024, with most of the posts being contract-specific.


Contract CR209 - West Coast station & tunnels
The final channel for the CRL contracts is for contract CR209 at West Coast station. A QR code is available for easy access to the channel and the latest post is dated 12 July 2024. Overall, the channel features mostly contract-specific updates.

We hope that the above allow you to gain access to the official Telegram channels for the various CRL contracts - although we think that you may glean more information from our blogs & social media channels than some of the Telegram channels. Nonetheless, feel free to follow the various channels to receive updates as & when they come in.

This post will also be available on Instagram & Facebook on 17 July 2024.

No comments: