Wednesday, July 31, 2024

N109A - Teck Ghee update Q2 2024

 

20 June 2024 - An aerial view of the junction of Ang Mo Kios Avenue 1 & 6 with Marymount
Road in end-Q2.

Over the past quarter, the major development over at Teck Ghee has been the road diversion of Ang Mo Kio Avenue 6. The diversion saw the roadway shifted further west to allow bored piling works to commence on the eastern side of the site. Along with the road diversion came a re-sizing of the roadway with each carriageway now only having 2 lanes instead of the 3 used formerly. When viewed from an aerial vantage point, the changes are quite apparent.

Works at the junction of Ang Mo Kio Avenues 1 & 6 with Marymount Road continued. Station exits will be located at the four corners of the junction here, with the subways connecting Exits 2 & 3 located within Bishan-Ang Mo Kio Park to be constructed by a rectangular bored tunneling machine. Ahead of the machine's delivery, construction of the launch and retrieval shafts had to be completed. Sheet piles were used to create the launch shafts within the park and retrieval shafts on the Ang Mo Kio side.

25 April 2024

25 April 2024

25 April 2024 - An aerial view of the construction site in early-Q2.

25 April 2024 - Sheet piling ongoing near the location of Exit 4.

30 May 2024

30 May 2024 - An aerial view of the work site prior to the road diversion seen in mid-Q2.

30 May 2024 - Continued sheet piling works at the site of Exit 4.

20 June 2024 - A view of the sheet piles beginning to form the retrieval shaft for the
rectangular tunnel boring machine drive from Exit 3 across the road.

20 June 2024 - The launch shaft for rectangular tunnel boring machine launching beginning to
take shape within Bishan-Ang Mo Kio Park. This will eventually form Exit 3.

20 June 2024 - On the other side of Bishan-Ang Mo Kio Park, the launch shaft for Exit 2 is
beginning to take shape as well.

20 June 2024 - Heavy machinery on site at Exit 1.

20 June 2024 - Steel piles awaiting use while others are already driven into the soil. It is likely
that the ones on the left are to be used as a decking of sorts.

20 June 2024 - An aerial view of the work site after the road diversion in end-Q2.

20 June 2024 - Progress of works at the site of Exit 4.

The approximate location of Exits 5 & 6 is where the road diversion has seen the roadway swing further west. Over the course of the past quarter, preparation works were underway to backfill soil over the roof slab of the expressway tunnels. Compacted soil was overlaid with a layer of crushed stone before the roadway was finally paved over. In mid-June, the roadway was swung over on a weekend. Work to mobilise machinery for the resumption of bored piling works began shortly after the road diversion was completed.

25 April 2024 - A view northwards from the location of Exit 5. Preparatory works are underway
ahead of the road diversion later in the quarter.

25 April 2024 - Soil backfilling works underway over the expressway tunnel roof slab.

30 May 2024 - A view of backfilling works completed over the expressway roof slab in mid-Q2.

30 May 2024 - One last look at the original layout of Ang Mo Kio Avenue 6 as a dual 3-lane
carriageway in mid-Q2.

20 June 2024 - An aerial view of the diverted, shrunken Ang Mo Kio Avenue 6. There is no longer
any dedicated bus lane along the roadway.

20 June 2024 - A view nrothwards of the diverted roadway.

20 June 2024

20 June 2024 - A view southwards of the newly diverted roadway.

With the road diversion in place, works will resume on bored piling for the western wall of the site. These works require round-the-clock construction for safety reasons to avoid sinkholes and collapse of the excavated pile. As such, residents may have to endure a period of noise for approximately another year while these works are carried out. Once the roof slab on this side can be cast, it is likely that excavation will continue below the slab, minimise noise generated from the site.

This post will also be available on Instagram & Facebook on 1 August 2024.

No comments:

Post a Comment