|
20 June 2024 - A view of heavy machinery on the south side of the station in end-Q2. |
The site of contract CR116 has been a busy one over the past quarter, with preparation works underway to begin construction at Exit 7 outside AMK Hub. This site has been one of the few that has yet to begin construction in any form while works progressed at the rest of the station site. One of the major observations over the course of the quarter was the slow ramping down of diaphragm walling works on the southern edge of the station as the works approached completion. Join us as we look back on the progress made over the past quarter.
Paid transfer connection to North-South Line (NSL) station, Exits 1, 2 & 6
This section of the station occupies the area south of the Ang Mo Kio Town Garden (East) and has been home to the betonite silos. Over the past quarter, the first phase of diaphragm wall works for the paid connection, Exit 2 & Exit 6 appear to have been completed.
|
20 April 2024 - An aerial view of the ongoing work at Ang Mo Kio Town Garden (East) in early-Q2. Heavy machinery can be seen near the existing NSL station. |
|
22 May 2024 - An aerial view of the ongoing work at Ang Mo Kio Town Garden (East) in mid-Q2. The heavy machinery near the NSL station had largely left the site. |
|
24 June 2024 - An aerial view of the ongoing work at Ang Mo Kio Town Garden (East) in end-Q2. The heavy machinery next to the NSL station was no longer on site. |
Existing NSL station works
As part of the upgrade of the existing Ang Mo Kio NSL station, major addition & alteration works need to be carried out to modify the layout of the station. Part of these works saw the closure of Exit D to be reconfigured into Exit 2 and part of the paid transfer link to the new Cross Island Line (CRL) station. A detour to the station's toilets was set up, cutting through the existing paid area of the concourse, separated only by temporary metal barricades.
|
20 April 2024 - A view of the existing Exit A of the station in early-Q2. |
|
20 April 2024 - Former shops that had been vacated for the modification works to be undertaken. |
|
20 April 2024 - A view of the station's existing ticket service kiosks in the concourse unpaid area. |
|
20 April 2024 - A view of the existing Exit D prior to its closure. |
|
20 April 2024 - Preparation work underway for the temporary corridor connecting to the station's toilets. |
|
20 April 2024 - A view of the temporary metal barriers that separate the paid and unpaid zones. |
|
20 April 2024 - Another view of the unpaid corridor created for commuters to access the station's toilets. |
|
20 April 2024 |
|
22 May 2024 - A view of the ticket service kiosk bank in the concourse fare unpaid area. |
|
22 May 2024 - A view of the since closed Exit D. The modified tactile guides can be seen on the floor leading to the new route to the toilets. |
|
22 May 2024 |
|
22 May 2024 |
|
24 June 2024 - A view of the station's Exit A in end-Q2. At this point, not many changes can be seen here. |
Intermediate Launch Shaft 1
Tunneling works also form part of the contract, linking Ang Mo Kio station with Teck Ghee station to the west. An intermediate launch shaft is located at the junction of Ang Mo Kio Avenues 3 & 6, near block 324. According to contractor Gammon-Bachy Soletanche, excavation works for the launch shaft were expected to be completed around July.
|
April 2024 - A view within the noise enclosure, looking at the ongoing excavation within the launch shaft. Source: LinkedIn |
|
20 June 2024 - An aerial view of the noise enclosure around the launch shaft in end-Q2. |
Exits 7 & 8The pair of exits will be located across Ang Mo Kio Avenue 8 from the existing NSL station and viaduct. Through the past quarter, preparatory works for the site of Exit 7 which will be located directly outside AMK Hub can be clearly seen. The large trees slowly disappeared over the course of the quarter, leaving the area slightly more bare and exposed. Eventually the covered linkway too will disappear when construction of the new exit commences with hacking works likely to be the first activity to commence.
Across the road lies Exit 8, which had previously completed the first phase of diaphragm wall works. We understand that a small section of the diaphragm wall was left to be completed after some utility diversion works were finished. This would allow for a mined subway tunnel to be constructed from the main station box, located east of the NSL viaducts, to connect with the exits on the western side.
|
20 April 2024 - An aerial view of the sites of Exits 8 (left) and 7 (right) as seen in early-Q2. |
|
20 April 2024 - A view of ongoing works at the site of Exit 8 in early-Q2. |
|
20 April 2024 - The future site of Exit 7 as seen in early-Q2. |
|
22 May 2024 - An aerial view of the sites of Exits 8 (left) and 7 (right) as seen in mid-Q2. |
|
22 May 2024 - A view of ongoing works at the site of Exit 8 in mid-Q2. |
|
30 May 2024 - The site of Exit 7, on the left, with trees since cleared in mid-Q2. |
|
24 June 2024 - An aerial view of the sites of Exits 8 (left) and 7 (right) as seen in end-Q2. |
|
24 June 2024 - A view of the site of Exit 8 in end-Q2. |
|
24 June 2024 - An aerial view of the site of Exit 7, with trees since felled to make way for construction commencement. |
Exit 10
The site for Exit 10 and its associated subway is located at the junction of Ang Mo Kio Avenue 3 and Street 42. With Street 42 having been diverted for some time now, soil improvement works began at the start of the quarter. Towards the end of the quarter, excavation work began at the site.
|
22 May 2024 - An aerial view of the Exit 10 subway site in early-Q2. |
|
22 May 2024 - A soil improvement rig at work. |
|
22 May 2024 - Steel piles were driven into the ground to act as earth retaining & stabilising structures. |
|
30 May 2024 - A view of ongoing works at the site as seen from street level in mid-Q2. |
|
30 May 2024 |
|
20 June 2024 - A view of ongoing works at the site as seen from street level in end-Q2. |
|
24 June 2024 - Excavation underway with the first layer of struts or waler beams being installed. |
|
24 June 2024 - A close up view of the ongoing works as of end-Q2. |
|
24 June 2024 - Excavation works taking place at the site. |
|
24 June 2024 |
Exit 11
The final site we're covering in this update will that of Exit 11, located right outside block 587. Through the quarter, heavy machinery has been mobilised to the site with diaphragm wall works commencing towards the middle of the quarter.
|
20 April 2024 - A view of the Exit 11 site as seen from street level in early-Q2. |
|
20 April 2024 - The site in front of block 587. |
|
20 April 2024 |
|
20 April 2024 - An aerial view of the site in early-Q2. |
|
20 April 2024 |
|
22 May 2024 - Machinery on site at Exit 11, with the noise barrier wall also completed in mid-Q2. |
|
22 May 2024 - The Exit 11 site as seen from street level. |
|
22 May 2024 |
|
22 May 2024 - The machinery on site includes a clamshell grabber machine and a mobile crawler crane. |
|
24 June 2024 - A view of the site in end-Q2 as seen from street level. Diaphragm wall construction was in progress. |
|
24 June 2024 - An aerial view of the site in end-Q2. |
|
24 June 2024 - A close up view of the heavy machinery on site. |
|
24 June 2024 |
|
24 June 2024 |
On the contract's official Telegram channel, the contractor updated that diaphragm walling works along the station's southern edge were completed at the end of July 2024. With that, preparation works can be expected to take place over the third quarter of the year to begin the process of diverting the roadway closer to the southern side so that diaphragm wall works can commence on the station's northern edge.
|
2 August 2024 Source: CR116 Telegram channel |
This post will be available on Instagram & Facebook on 7 August 2024.
No comments:
Post a Comment