Tuesday, March 25, 2025

P105 - Roadshow exhibition for upcoming footpath closures

 

13 March 2025 - A view of the exhibition boards at the roadshow to update commuters on the
upcoming footpath closures in the vicinity.

The contractor for contract P105 - Woh Hup Pte Ltd - recently held a roadshow over two days at the Punggol station to inform commuters of the upcoming footpath closures. Some of these footpath closures will come in tandem with road diversions to be implemented while others will be implemented in line with phased works for the new underground station.

Wednesday, March 5, 2025

N109A - Completion of Exit 3 subway by RTBM

February 2025
Source: LinkedIn

Tunneling work underneath Ang Mo Kio Avenue 1 for the subway connecting Exit 3 with the Teck Ghee station box was recently completed in February 2025. The contract used a Rectangular Tunnel Boring Machine (RTBM) that employed a technique similar to pipe jacking to complete the 50m long subway. This represents a significant milestone in the construction of the Cross Island Line (CRL).

Saturday, March 1, 2025

CPE - A snapshot in February 2025

A view of Riviera and Punggol Cross Island Line station sites in February 2025.

Work is well underway for the construction of the Cross Island Line - Punggol Extension (CPE) which will see the line connecting Punggol and Pasir Ris stations via a branch of the Cross Island Line (CRL). Tunneling work for the majority of the alignment will be completed by a large diameter tunnel boring machine (TBM) - named Elizabeth - from a launch shaft just next to Pasir Ris Camp. Two drives will be used, one westwards ending at Punggol and a second eastwards, ending at Elias station. Before the arrival of TBM Elizabeth, ground improvement works were being carried out along Punggol Central. Diaphragm wall construction at the two station within Punggol were also well underway ahead of the TBM's arrival in a few years' time. More details on the works taking place after the jump.