Thursday, July 6, 2023

CR113 - Serangoon North update Q2 2023

10 June 2023 - A view of the construction sites at Serangoon North.

 Over at contract CR113, work has been picking up speed with the preparation of several sites completed and moving onto site set up with equipment being moved in. This contract is for the construction of Serangoon North station and does not involve any tunneling works, which will be carried out by neighbouring contracts CR112 to the east and CR115 to the west. The station itself occupies a fairly long site, with the eventual station stretching for about 700m, it is undoubtedly one of the longest stations and will involve a complex construction.


10 June 2023 - Betonite silos set up at the worksite in Serangoon North commercial centre.

The site at the town centre has been set up to allow betonite silos to be house there ahead of diaphragm wall construction works. The eventual station will feature 5 exits, of which one will be located at the town centre area. This exit - number 1 - is likely to be the main entry and exit point for the station. The cooling tower is likely to be integrated on top of the station exit here.

10 June 2023 - A view of the street-level pedestrian crossing replacing the pedestrian overhead
bridge.

10 June 2023 - Work site for station Exit 2.

10 June 2023 - Worksite preparation in progress along Ang Mo Kio
Avenue 3.

29 June 2023 - A view along Ang Mo Kio Avenue 3.

29 June 2023 - Near the junction with Serangoon North Avenues 1 and 3.

29 June 2023 - Looking ahead at the pedestrian overhead bridge being decommissioned.

29 June 2023

29 June 2023 - The covered shelter of the pedestrian bridge being removed progressively.

29 June 2023

29 June 2023

29 June 2023 - A view of the slip road at the junction with Yio Chu Kang Road.

29 June 2023 - Works underway for a subway to exit 4 at the site of Bowen Secondary School.

29 June 2023

29 June 2023 - A view of the slip road with Bowen Secondary School site of Exit 4 in the
background.

29 June 2023 - Hoarding going up at the slip road towards Hougang Avenue 2.

29 June 2023 - Bowen Secondary School site for Exit 4.

29 June 2023

29 June 2023

29 June 2023

29 June 2023

10 June 2023 - Upcoming work activities.

10 June 2023 - Circular to residents.

10 June 2023

At other areas along the station footprint, work is ongoing to prepare the various stretches for construction work. Following the diversion of utilities and services, work can begin on the station retaining walls. Before this commences, noise insulation barriers will be constructed to minimise noise disturbances to residents living next to the work sites.

19 March 2023 - A view of the work site for Exit 1 at the town centre,
betonite silos have been set up here currently.

19 March 2023

19 March 2023 - The pedestrian overhead bridge with shelter intact previously.

23 March 2023 - Betonite silos being set up.

23 March 2023 - Street level pedestrian crossing.

23 March 2023

One of the key activities was the opening of a street-level pedestrian crossing to replace the pedestrian overhead bridge (POB). This crossing has been since commissioned and the POB since closed to pedestrian access. Work has been going on to dismantle the shelter before the bridge is entirely demolished to make way for traffic diversions and other construction works.

This post will also be available on Instagram & Facebook from 7 July 2023.