Wednesday, December 27, 2023

CRL1 year-end update 2023

 

10 stations of the Cross Island Line's phase 1 as at end-2023.
Aviation Park & Defu are not represented in this post.

Sorry this post was a little delayed - got caught up between travelling & work. But we're here and made it to 27th December after all. For this post, we're covering the 10 stations that we have the most pictures of along the Cross Island Line (CRL)'s phase 1. The 2 stations not covered in the post today are Aviation Park and Defu. We may cover them at a later time. Nonetheless, it has been an eventful year for the CRL with the groundbreaking ceremony being held in January 2023. Construction has been well under way at all sites with work in full swing for the construction of the earth retaining & stabilising structures (ERSS). Several intermediate launch shafts have been built as well and excavation commenced at a few sites in particular.

Please be fair warned that this post is a mega-post and extremely photo-heavy. It may suck up a lot of your bandwith after the jump.

Wednesday, December 6, 2023

CRL2 - Contract award for CR209

 

A render of one of the station exits - likely Exit 2.
Source: LTA

A render of the station's interior.
Source: LTA

Today, the Land Transport Authority (LTA) announced the award of contract CR209 for the construction of West Coast station & associated tunnels under the Cross Island Line phase 2. Contract CR209 is the fourth contract under phase 2 to be awarded - the other contract being contract CR202 for the large diameter tunnel through the Central Catchment Nature Reserve and contracts CR205 and CR208 for the construction of King Albert Park and Clementi interchange stations only respectively.

Thursday, November 23, 2023

N109A - Teck Ghee update Q3 2023

19 August 2023 - Installation of rebar visible within the excavated trench.

Work at Teck Ghee station's site is progressing with the excavation of the western half of the tunnels for the North-South Expressway underway. Looking at the work taking place, it may be likely that the structure on the western side will be completed before earth is back-filled on top of the roof slab and work begins on work for the eastern half's structure. At this point, Ang Mo Kio Avenue 6 which travels right on top of the future tunnels has been pushed to the eastern side to allow for sufficient space to create a work site on the western side which is where the tunnels are being constructed.

Friday, November 10, 2023

CRL1, CPE & CRL2 - A snapshot in October 2023

 

Top (L - R): CR105 - Large diameter tunnel, CR3 - Loyang, CR4 - Pasir Ris East
Middle (L - R): CR5/CP1 - Pasir Ris, CR6 - Tampines North, CR7 - Defu
Bottom (L - R): CR8 - Hougang, CR9 - Serangoon North, CR10 – Tavistock


Top (L - R): CR11 - Ang Mo Kio, CR12 - Teck Ghee, CR13 - Bright Hill
Middle (L - R): CP2 - Elias, CP3 - Riviera, CR15 - King Albert Park
Bottom (L - R): CR16 - Maju, CR17 - Clementi, CR18 - West Coast


Here's a look at the progress made at the various Cross Island Line (CRL) sites across Phases 1, 2 & the Punggol Extension in October 2023.

Thursday, November 9, 2023

CR116 - Ang Mo Kio update Q3 2023

 

19 August 2023 - A view of the progress of construction around the existing North-South Line
(NSL) Ang Mo Kio station.

Over Q3, works have progressed at the Ang Mo Kio station site. Significant progress has been made at the launch shaft site as well as several exit worksites where diaphragm wall excavation works have commenced. Soil treatment work is also being carried out at Exit 8 ahead of excavation there.

Thursday, November 2, 2023

CR115 - Tavistock update Q3 2023

 

21 September 2023 - A view of the road diversion implemented for Ang Mo Kio Avenue 3 at
the site of Tavistock station.

Over Q3 2023, road diversions have been put in place at Tavistock station and more machinery has moved in to the site. With works in full swing, diaphragm wall excavation is due to commence in mid-Q4 2023. We take a closer look at the progress made over the past quarter in this post.

Thursday, October 26, 2023

CR113 - Serangoon North update Q3 2023

 

21 September 2023 - A view of the station site at the town centre of Serangoon North. Exit 1
will be located there.

The major change that took place over the past quarter was the commencement of diaphragm wall excavation at the Exit 1 site. Located right smack in the heart of the town centre, this will be the site of the main station entrance. Formerly some pile load testing was conducted here before the betonite silos moved in. Subsequently, a hydrofraise machine was also brought in to begin set up. Excavation for the diaphragm wall panels has since begun in Q3 2023.

Further along towards the eastern end of the station is Exit 4, which is located adjacent to Bowen Secondary School. The work site here has made progress with noise barriers being installed and a road diversion implemented. Across the road from the school, work is being carried out with the installation of sheet piles - this may potentially be used as a retaining wall to divert the roadway for the excavation of the station box and mined subway. Over at other sites, preparation has also been carried out ahead of the commencement of diaphragm walling works.