19 August 2022 - The hydrofraise machine in position & in action excavating the diaphragm wall trench. |
This past week, excavation works commenced at Hougang station as part of works to install diaphragm walls (d-walls) to support station construction works. As part of the works, the hydrofraise machine is used to lower down the vertical cutters which rotate to remove soil. The excavated area is prevented from collapsing through the use of betonite slurry, a dense liquid that is pumped in by the machine from storage reservoirs. Do check out the videos which explain the process.
19 August 2022 - A view of the site looking southwards. |
19 August 2022 - The hydrofraise machine as seen from the side. |
19 August 2022 - Crawler crane on site with rebar cages to be lowered into the excavated trench. |
19 August 2022 - Guide walls for the trench excavation. |
Meanwhile, works are on-going to expand the relocate and expand bus stops along Hougang Avenue 10 ahead of the upcoming closure of Hougang Central (Minor) on 28 August 2022. As several bus routes will be affected by the closure of this short route, the bus stops are being lengthened to cater for additional buses calling at the stops.
19 August 2022 - A view of Hougang Central (Minor) looking southwards. |
19 August 2022 - Eastbound bus stop along Hougang Avenue 10. |
19 August 2022 - Westbound bus stop along Hougang Avenue 10. |
19 August 2022 - A new set of pedestrian crossing traffic lights being put in place ahead of the closure of Hougang Central (Minor) on 28 August 2022. |
Other works are also continuing along Hougang Central (Major) as a traffic diversion is expected to occur some time soon - probably in conjunction with the closure of Hougang Central (Minor). Two bus stops along the eastbound lanes of the roadway had been shifted earlier in July. It is noted that works now have included excavation of soil to create a new roadway where the bus stop used to sit previously.
21 August 2022 - Clearing the side table near the bus stop along Hougang Central (Major). |
21 August 2022 - New bus stop shelter along diverted section of Hougang Central (Major). |
21 August 2022 - A view of the upcoming diversion for Hougang Central (Major), including the new bus stop shelter. |
Do watch this space as we update next week with the closure of Hougang Central (Minor).