9 September 2022 - An aerial view of the Defu station site looking eastwards.

Contract CR111 is for the construction of Defu station and twin bored tunnels towards Hougang station. The contract was awarded to a joint venture between Gamuda Berhad Singapore Branch and Wai Fong Construction in February 2022. Since then, concrete barriers have been placed on site and fencing has been atop the barriers.


2 May 2022 - An aerial view of the Defu station site, noticeably different in the background.

17 June 2022 - A view of the area near the junction of Tampines Road
and Defu Avenue 2. Utility diversion works were taking place.

22 August 2022 - Concrete barriers being set up around the work site.

17 June 2022 - A view of the site along Tampines Road.

22 August 2022 - Concrete barriers a bit further down from the junction.

22 August 2022

22 August 2022 - Hoarding going up in the background.

9 September 2022 - Contract CR111 site offices being set up.

Hoarding has also been set up against the back of the site along Tampines Road, abutting the workshops in the area. Across the road, the site offices are being set up as well, along Serangoon River Road. Works will ramp up soon, like at other station sites along the line.

This post is also available on Instagram.