14 September 2022 - A view of the closed section of Hougang Central as seen from Hougang Avenue 10. A more permanent pavement has been constructed. |
31 August 2022 - A view of the closed section of Hougang Central as seen from Hougang Avenue 10. |
On the 28th August, a portion of Hougang Central was closed to facilitate the construction of the Hougang interchange station. It has been about 2 weeks since the road's closure. Today, we take a look at the changes implemented and progress at this particular area of the site.
19 August 2022 - A view of the closed section of Hougang Central prior to closure. |
Seen from the northern end, the changes are pretty obvious as hoarding has gone up where the road used to be. A permanent pavement has also been constructed over the roadway to allow pedestrians to walk across with ease.
14 September 2022 - A view of the closed section of Hougang Central. |
14 September 2022 - A view of the closed road section. |
31 August 2022 - A view of Hougang Central (Minor) following its closure as seen from Hougang Central (Major). |
31 August 2022 - A view of the old foot path along Hougang Central (Major). |
31 August 2022 |
31 August 2022 |
31 August 2022 - The original bus stop shelter opposite the Hougang Central interchange has since been demolished. |
Seen from the southern end, there are still on-going works as a road diversion of Hougang Central (Major) is being prepared. Hoarding has come down to unveil a newly diverted pedestrian foot path and accompanying bus stop. However, the roadway is not yet paved and is pending for the demolition of the existing pedestrian pathway so that paving can take place. Drainage is also being constructed further down to support the upcoming road diversion.
This post is also available on Instagram.
No comments: