Friday, October 6, 2023

CRL1 - A snapshot in September 2023

 

Overview of CRL1 stations CR4 - CR11 & Contract CR110 as at September 2023.
Top (L - R): CR4 - Pasir Ris East, CR5/CP1 - Pasir Ris, CR6 - Tampines North
Middle (L - R): CR7 - Defu, CR8 - Hougang, CR9 - Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR110 – Large diameter tunnel

Our snapshot update for the Cross Island Line (CRL) phase 1 in the month of September 2023 is here. We have also begun the Q3 updates for some stations, so those updates will be more detailed than the ones reflected here. Nonetheless, do enjoy the brief update on the 9 contracts for September.

CR4 - Pasir Ris East (Contract CR107)
In a nutshell: Noise barriers have been completed at the site. Diaphragm wall works are concentrated at the launch shaft to be handed over to contract CR106. Read more here.

17 September 2023

17 September 2023

17 September 2023

CR5 | CP1 - Pasir Ris (Contract CR108)
In a nutshell: Noise barrier installation works were underway in front of Costa Ris while Pasir Ris Central was being prepared to serve as an alternative route during the closure of Pasir Ris Drive 1. Diaphragm wall works continued at both the western crossover box & eastern cut & cover tunnels. Read more here.

17 September 2023

17 September 2023

17 September 2023

17 September 2023

CR6 - Tampines North (Contract CR109)
In a nutshell: Excavation work is underway at the northern launch shaft which will serve tunnel boring machines (TBMs) tunneling towards Pasir Ris. Diaphragm wall construction continues for the southern launch shaft that will serve TBMs boring towards contract CR110.

17 September 2023

17 September 2023

Large diameter bored tunnels – Paya Lebar Air Base (Contract CR110)
In a nutshell: Diaphragm wall construction and excavation works are being done concurrently at the launch shaft, site of Facility Building 3. At the reception shaft, preparatory work is underway.

17 September 2023

17 September 2023

17 September 2023

CR7 - Defu (Contract CR111)
In a nutshell: Another road diversion has taken place, pushing the eastbound roadway south. Diaphragm walling works have commenced at the launch shaft at the western end of the station.

21 September 2023

21 September 2023

21 September 2023

21 September 2023

CR8 - Hougang (Contract CR112)
In a nutshell: Rebar installation was being done ahead of slab casting for the second level in the launch shaft. King posts were being installed at the northern site as well while diaphragm wall works continued at the southern site.

14 September 2023

14 September 2023

14 September 2023

21 September 2023

CR9 - Serangoon North (Contract CR113)
In a nutshell: Works have picked up the pace with the installation of noise barriers under way and the closure of pedestrian footpaths.

21 September 2023

21 September 2023

21 September 2023

21 September 2023

CR10 - Tavistock (Contract CR115)
In a nutshell: Roadway has been diverted, with the bus stop following suit at the end of the month. Heavy equipment has been moved in progressively on site.

21 September 2023

21 September 2023

21 September 2023

CR11 - Ang Mo Kio (Contract CR116)
In a nutshell: Diaphragm wall work continues at the various station exits.

28 September 2023

28 September 2023

29 September 2023

A similar but consolidated (a.k.a. simplified) post will be available on Instagram & Facebook on 7 October 2023.