Saturday, September 3, 2022

CR115 - Tavistock station exhibition

3 September 2022 - The mini exhibition for Tavistock station construction
was held in Tavistock Park for residents living around the area.

3 September 2022 - Tavistock station mini-exhibition.

3 September 2022 - Tavistock station mini-exhibition.

TAVISTOCK PARK, Singapore - The Land Transport Authority (LTA) together with contractor Sato Kogyo on Saturday afternoon, held a mini-exhibition at Tavistock Park for residents in the area. With an aim to educate the residents on the upcoming works for the station, several exhibits detailing various aspects of the construction were set up at one of the pavilions within the park. A sizeable crowd was noted at the beginning of the exhibition, with several participants interacting with LTA staff who were carrying A3 sized print outs to explain the stages of construction to attentive residents.

Monday, August 22, 2022

CR112 - D-wall excavation commences

 

19 August 2022 - The hydrofraise machine in position & in action excavating the diaphragm wall
trench.

This past week, excavation works commenced at Hougang station as part of works to install diaphragm walls (d-walls) to support station construction works. As part of the works, the hydrofraise machine is used to lower down the vertical cutters which rotate to remove soil. The excavated area is prevented from collapsing through the use of betonite slurry, a dense liquid that is pumped in by the machine from storage reservoirs. Do check out the videos which explain the process.

Saturday, August 20, 2022

CR108 - Checking in at Pasir Ris

 

An aerial view of the existing Pasir Ris station with
the Pasir Ris Central worksite.

It's been a few months since we last came by here. Things are definitely ramping up with so much going on at the site. Machines coming in, set up work going on, reconfiguration works and exit & road closures are all in full effect. The construction site can be broken into about 3 smaller zones - along Pasir Ris Drive 8, Pasir Ris Central & Pasir Ris Street 51.

Friday, August 5, 2022

CRL2 - Speculated Station Locations

A map of the expected phase 2 of the Cross Island Line. Own production.

As it has been more than 2 years since Cross Island Line (CRL) Punggol Extension was announced, we are expecting news of the next phase of the line to be announced this year. With an expected completion date of 2032, we foresee tenders for advanced contracts to be published soon. Earlier in June, pre-qualifications for 8 contracts for the second phase of the line were called for.

The Urban Redevelopment Authority (URA) Long-Term Plan.
Source: URA

The Urban Redevelopment Authority (URA) also published the latest Long-Term Plan in June 2022 which showed the notional full alignment of the CRL. By overlaying the long-term plan map over a geographic map, we were able to collaborate the supporting data and information with the latest sightings of soil investigation works to compile a list of probable station locations for the CRL2 section. This section of the CRL will continue from the tunnel section directly crossing below the Central Catchment Nature Reserve (CCNR), and ends at Jurong Lake District.

We expect that there will be a total of 6 stations in this section, which stretches over 15km consisting of 5km below the CCNR, and 10km of tunnels between the 6 stations.
Geographical map of our expected CRL2 stations & alignment based on URA's long term plan.


Monday, August 1, 2022

Follow SG MRT Construction on Instagram

 

Follow us by scanning the QR code above in the Instagram app, which will bring you directly to SgMC's Instagram page. Alternatively, search for us @sgmrtconstruction or visit https://www.instagram.com/sgmrtconstruction/

The team behind Cross Island Line Construction is proud to bring you SG MRT Construction (SgMC), an Instagram page that will allow us to bring you more frequent, bite-sized, image-driven updates!

SgMC will complement our existing blogs, allowing the team to offer more timely updates, and even content that may not constitute a full blog post. 

Through stories & highlights, we want to bring you snappy pictorial [maybe even a video or two :) ] updates on the various rail lines, including the existing lines that we do not previously cover on the blogs.

Each Instagram post will carry a unique frame design, for ease of distinguishing updates on different lines and stages. 

We also want to interact more with you, our dear reader! Slide into our DMs with your photos, videos, and tipoffs - we would love to hear from and feature you :) 

We are also planning an IG story engagement this national day holiday, so do join us then! Check back for more deets as they drop soon.

Fret not, the blogs are here to stay. They'll carry more detailed writeups and deep dives. Do continue to visit for the full deets - we will cross post updates across both platforms. 

So do drop by SgMC on Instagram - you can view it on a web browser too if you do not have an Instagram account - and follow us for a new way of connecting & receiving updates.

Follow us by scanning the QR code above. Alternatively, search for us @sgmrtconstruction or visit https://www.instagram.com/sgmrtconstruction/

Thursday, July 28, 2022

CR112 - Upcoming bus route amendments

 

28 July 2022 - The hydrofraise machine boom lifted into vertical position. This machine will be
used to dig trenches for the construction of diaphragm walls to enable excavation of the station box.

Things are starting to get busy at Hougang Cross Island Line (CRL) station site. Today, the hydrofraise machine was lifted into vertical position, marking a step closer to the construction of diaphragm walls for the station. It also means that we are a step closer to the eventual closure of Hougang Central (Minor). This is a stretch of road linking Hougang Central (Major) and Hougang Avenue 10, roughly parallel to the upcoming station. In view of this, there will be amendments to bus services that use Hougang Central (Minor) as detailed by operator SBS Transit today.

Tuesday, July 26, 2022

CR116 - Ang Mo Kio station renders

 
The current exit A which will be renumbered exit 1 in the expanded station.
Source: CR116 Ang Mo Kio Interchange Station and Tunnels Site Office

Recently while searching online, the team came across several renders of the Ang Mo Kio interchange station. As expected, major works are anticipated ahead of the station's construction. Several more exits will be added to the station complex, including a bridge parallel to the existing MRT line that will have active mobility features included.