CRL - A snapshot in February 2024

 

Overview of CRL1 stations CR3 - CR13 as at mid-to-late February 2024.
Top (L - R): CR3 - Loyang, CR5/CP1 - Pasir Ris, CR6 - Tampines North
Middle (L - R): CR7 - Defu, CR8 - Hougang, CR9 - Serangoon North
Bottom (L - R): CR10 – Tavistock, CR11 – Ang Mo Kio, CR13 - Bright Hill


Overview of CPE & CRL2 stations CP02 - CP04 & CR15 - CR18 as of mid-to-late February 2024.
Top (L - R): CP02 - Elias & CP03 - Riviera
Middle (L - R): CP05 - Punggol, CR15 - King Albert Park, CR16 - Maju
Bottom (L - R): CR17 - Clementi & CR18 - West Coast

The first few months of the year have quickly past and we're slowly getting back into the monthly routines. Here's a snapshot update of the Cross Island Line (CRL)'s various stages of construction for the month of February with work started on phase 1 and the Punggol Extension. The latest phase announced - phase 2 - has also begun early works which we also explore in this update.

Phase 1
Works have been going on for some time now with all sites busy creating the earth retaining & stabilising structures (ERSS). This is probably one of the nosier and causes the most disruption as the machinery on site comes into close proximity to other buildings. As excavation takes place for the station's perimeter, nearby buildings may observe some vibration. Once this stage of the works are completed, things generally get quieter and the vibrations may not be as noticeable.

CR3 - Loyang (Contract CR106)
In a nutshell: Diaphragm walling works are continuing to progress. Some parts of the diaphragm wall on the southern end of the station have been uncovered and work on the constructing the capping beam for these is underway.

25 February 2024

25 February 2024

25 February 2024

25 February 2024

CR5 | CP1 - Pasir Ris (Contract CR108)
In a nutshell: With the Pasir Ris Drive 1 realigned within the Costa Ris Build To Order compound, work has begun on the removal of the old roadway to make way for diaphragm wall works along the south boundary of the station. To the east, works for diaphragm wall construction are still concentrated along the northern edge.

29 February 2024

29 February 2024

29 February 2024

CR6 - Tampines North (Contract CR109)
In a nutshell: More of the station and cut & cover tunnel section to the south has been excavated. Excavation works are also taking place within the launch shafts for the Tunnel Boring Machines (TBMs), which have arrived and are being stored on site at the moment.

25 February 2024

25 February 2024

25 February 2024

25 February 2024

CR7 - Defu (Contract CR111)
In a nutshell: Diaphragm walling and ground improvement works are in progress at the site.

25 February 2024

25 February 2024

25 February 2024

25 February 2024

CR8 - Hougang (Contract CR112)
In a nutshell: Excavation works continue within the launch shaft to reach the base level for casting of the base slab which will support the TBMs once lowered into the shaft. On the southern end of the station, king post installation was taking place.

25 February 2024

12 February 2024

12 February 2024

12 February 2024

25 February 2024

CR9 - Serangoon North (Contract CR113)
In a nutshell: Diaphragm wall works continue across various locations of the site. Road diversions have been put into place at the major traffic junction along Ang Mo Kio Avenue 3 as works progress.

12 February 2024

12 February 2024

12 February 2024

12 February 2024

CR10 - Tavistock (Contract CR115)
In a nutshell: Diaphragm wall works have been completed at Exit 4 but continue along the southern edge of the station. Excavation works have progressed at the launch shaft and a gantry crane was observed to have been delivered to site.

12 February 2024

12 February 2024

12 February 2024

12 February 2024

12 February 2024

CR11 - Ang Mo Kio (Contract CR116)
In a nutshell: Diaphragm wall works continue east of the existing station to form the perimeter of the new station box. With Exit D of the existing North-South Line (NSL) station due to close for upgrading & expansion works, Exit B has been widened to cater for additional traffic loads.

15 February 2024

12 February 2024

12 February 2024

12 February 2024

12 February 2024

CR13 - Bright Hill (Contract CR117)
In a nutshell: Preparatory works for a road diversion were being carried out, with the diversion coming into effect in the latter part of the month. Bored piling works continue elsewhere at the station site.

12 February 2024

12 February 2024

12 February 2024

12 February 2024

12 February 2024

Punggol Extension
The Punggol Extension is a sort of weird, in-between, half-phase of the line. Nonetheless, work is now in full swing at all 3 station sites with Elias station having recently cleared the site of vegetation. Over and Riviera and Punggol stations, ERSS works have begun.

CP02 - Elias (Contract P102)
In a nutshell: Site clearing has taken place with large tracts of land now free from vegetation. Preparatory works for a load test pile were underway.

29 February 2024

29 February 2024

29 February 2024

29 February 2024

CP03 - Riviera (Contract P103)
In a nutshell: Diaphragm wall works have commenced with road diversions in place. There will be further road diversions being carried out as work moves further west. The launch shaft for TBM Elizabeth is also being constructed next to Pasir Ris Camp.

29 February 2024

29 February 2024

29 February 2024

29 February 2024

CP04 - Punggol (Contract P105)
In a nutshell: A pedestrian overhead bridge was dismantled and an underpass at Punggol station was closed - both were replaced with street-level crossings. Diaphragm wall works have commenced along the cut & cover tunnel section west of the station complex.

29 February 2024

29 February 2024

29 February 2024

29 February 2024

Phase 2
Construction sites along the line's most recently announced phase are slowly coming to life. Early works have begun at King Albert Park, Clementi and West Coast station while advanced works are in progress at Maju. As the contracts for Turf City and Jurong Lake District stations have yet to be awarded, we have not visited these sites for the moment.

CR15 - King Albert Park (Contract CR205)
In a nutshell: Soil investigation works have commenced at the end of Blackmore Drive and hoarding works were underway along Old Holland Road. Read more about the station's construction kick off here.

15 February 2024

15 February 2024

15 February 2024

CR16 - Maju (Contract CR206)
In a nutshell: The advanced works contract CR2016, is still in progress and actual contract CR206 works have yet to begin.

15 February 2024

15 February 2024

15 February 2024

CR17 - Clementi (Contract CR208)
In a nutshell: Demolition of the former Clementi Police Division HQ is underway. The demolition of the 3 HDB blocks selected for the Selective En-bloc Redevelopment Scheme (SERS) has been completed. Soil investigation work has also begun along the station's footprint.

24 February 2024

24 February 2024

24 February 2024

24 February 2024

CR18 - West Coast (Contract CR209)
In a nutshell: The former Tanglin Secondary School has been hoarded up and preparation works for its eventual demolition are underway.

24 February 2024

24 February 2024

24 February 2024

A similar but consolidated (a.k.a. simplified) post will be available on Instagram & Facebook on 9 March 2024.