|
12 February 2024 - A view of the Tavistock station site in mid-Q1. |
|
21 March 2024 - A view of the Tavistock station site in end-Q1. |
Contract CR115 for the construction of Tavistock station and tunnels connecting to both Ang Mo Kio and Serangoon North station has seen great progress accomplished over the past quarter. Diaphragm wall works have been completed at the Exit 4 site and the launch shaft is well on its way to completion ahead of tunneling works commencing.
|
12 February 2024 - Heavy equipment at the site of Exit 1. |
|
21 March 2024 - Rebar cages for the diaphragm walls at the Exit 1 site in end-Q1. |
|
12 February 2024 - A view of the southern edge of the station in mid-Q1. |
|
12 February 2024 - Exit 4 seen in the distance. |
|
21 March 2024 - The station southern edge in end-Q1. |
|
21 March 2024 - Exit 4 at the end of Q1. |
Launch shaft
The launch shaft has made great progress over the past quarter, with excavation works about reaching base level. According to circulars seen at the HDB blocks nearby, excavation is expected to continue up to April 2024. Thereafter, a noise enclosure is due to be built over the top of the launch shaft to insulate the residents from noise generated as a result of tunneling works.
|
12 February 2024 - A view of the launch shaft during Chinese New Year. |
|
12 February 2024 - The launch shaft seen from the other side of the former Teck Ghee Park. |
|
12 February 2024 - Components of a single, lone gantry crane are seen on site. |
|
12 February 2024 - Excavation of the launch shaft has progressed far beneath the eye's view. |
|
21 March 2024 - Two gantry cranes are now on site and installed in end-Q1. |
|
21 March 2024 - A close up view of the gantry cranes. |
|
21 March 2024 - A view of the launch shaft as it prepares for the commencement of tunneling works. |
|
21 March 2024 |
|
21 March 2024 |
Tunnel Boring Machine (TBM)
The TBM is expected to be delivered to site in early April 2024, with the contractor & Land Transport Authority (LTA) providing early notice to residents via Telegram. We expect that there will be approximately 3 TBMs used for this contract. 2 should be launched from the shaft and begin tunneling towards Tavistock station and thereafter, through the station box and onwards to Serangoon North. The remaining TBM will tunnel towards Ang Mo Kio and be reassembled at the launch shaft for a repeat journey to the station.
|
An infographic announcing the delivery date for components of the TBM. |
|
A view of one of the tunnel boring machines to be used for contract CR115. Source: CREC |
As Q1 comes to a close, we look forward to the arrival of the TBM at the launch shaft which represents a step closer to tunneling works beginning for the line. Do stay tuned for updates as we bring them to you.
No comments:
Post a Comment